RSK-0024Sheikh Najjar Industrial City Rehabilitation

Ground-improvement costs up after the geotechnical survey

16HighEscalatedMaterial

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

The geotechnical survey found softer soil and higher groundwater than the design study assumed

Preventive controls

  • A change request for the extra ground improvement
  • Value engineering of the foundation solution with the consultant

1 / 2

Event

Ground-improvement costs up after the geotechnical survey

16HighTrigger

The change request is not approved at the next CCB meeting

Contingency

Treat the ground in two stages, the ready southern plots first so factories can return

Impact

SYP 565M of extra ground improvement and a 75-day extension

SYP 562.5M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
16High

Residual

5
4
3
2
1
1
2
3
4
5
6Low

Exposure

SYP 562.5M

Residual

⁦63⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 6 days ago

  1. Project manager

    Eng. Youssef Shehabi

    Currently followed up here
  2. Programme manager

    Current level

    Eng. Youssef Shehabi

    Automatically at 15 days unreviewed · in 9 days
  3. 3

    PMO director

    Dr. Reem Al-Qabbani

    Automatically at 20 days unreviewed · in 14 days
  4. 4

    Executive Council

    Dr. Samer Al-Daqqar

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦1⁩ of ⁦2⁩ done
  • A change request for the extra ground improvement

    Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy
    Done2026-10-062026-10-06
  • Value engineering of the foundation solution with the consultant

    Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy
    In progressIn 15 days2026-11-12

Trigger

The change request is not approved at the next CCB meeting

Contingency

Treat the ground in two stages, the ready southern plots first so factories can return

Esc