CR-2026-007Sheikh Najjar Industrial City Rehabilitation

Additional ground improvement after the geotechnical survey

ScopeSubmittedImpact level: Major1 day overdue2026-10-27

Justification and the cost, schedule and risk impact, with a recommendation.

Electronic form

Impact analysis

Before and after — as it will show in the baseline if approved

Cost

+SYP 562.5M

Current budgetSYP 7.2B

After the changeSYP 7.7B

+7.9%

Schedule

+⁦75⁩ d
  • Baseline finish2027-03-31
  • New finish2027-06-14

Risk

−10

Benefits

+5%

A 50-year design life for the roads and networks of the industrial plots

⁦+5⁩% of expected benefits

Reason for change

The geotechnical survey found softer soil and higher groundwater than expected

Justification

Without it the foundations miss the required safety factor

PMO recommendation

Approve with conditions

Impact analysis in progress at the national PMO

Approval workflow

  1. Submitted

    Eng. Youssef Shehabi

    Done2026-10-06

  2. PM review

    Eng. Youssef Shehabi

    Done2026-10-07

  3. 3

    Impact analysis

    Kinan Azzam

    Now2026-10-11

  4. 4

    Finance & procurement

    Rasha Al-Mudarres

    Later

  5. 5

    Project owner’s acceptance

    Eng. Wassim Al-Azm

    Later

  6. 6

    Change committee recommendation

    Dr. Ziad Al-Atassi

    Later2026-10-29

  7. 7

    Executive Council decision

    Dr. Samer Al-Daqqar

    Later

  8. 8

    Baseline updated

    Eng. Youssef Shehabi

    Later

Why this route

The route is built from the request’s kind and impact level under the approved authority matrix.

Impact levelMajorAbove SYP 125M or 90 days

  • A cost impact of SYP 562.5M is above SYP 125M — «major»: the Change Committee recommends and the Executive Council decides.
  • It has a financial link, so Finance & Procurement take part before the decision.
  • It changes scope or deliverables, so the project owner must accept it.

Change committee vote

Members vote before or during the meeting; the decision is taken once quorum is met

Change Committee — meeting 4229 October 2026 13:00Meeting room 3 — fifth floor
  • Dr. Ziad Al-AtassiDeputy President, Strategy & PerformanceDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.syChairNot voted
  • Dr. Reem Al-QabbaniDirector, National Project Management OfficeDr. Reem Al-QabbaniDirector, National Project Management OfficeP-002reem.alqabbani@psa.gov.syYouNot voted
  • Omar Al-NahhasSenior Finance & Contracts SpecialistOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.syNot voted
  • Rasha Al-MudarresDirector General, Finance & ContractsRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.syNot voted
  • Eng. Rita GhanemEnterprise ArchitectEng. Rita GhanemEnterprise ArchitectP-031rita.ghanem@psa.gov.syNot voted
  • Eng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syNot voted
0/6⁦4⁩ short of quorum
  • Approve0
  • Approve with conditions0
  • Reject0
  • Abstain0

⁦4⁩ short of quorum · Awaiting the change committee’s decision in meeting ⁦42⁩

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close