RSK-0025Sheikh Najjar Industrial City Rehabilitation
Late works approvals from Aleppo Governorate
A risk's detail, response, contingency and residual risk.
Risk statement
From cause to event to impact — with the preventive controls before the event and the contingency after it
Cause
Updated regulations and several permit authorities (administrative units, Civil Defence)
Preventive controls
- Early contact with the competent authorities
- A compliance checklist before every submission
2 / 2
Event
Late works approvals from Aleppo Governorate
A permit application is refused or returned
Contingency
Submit a design alternative that meets the rules
Impact
Late permits and design changes
Assessment
The level before and after the response
Inherent
Residual
Exposure
SYP 150M
Residual
67% off the score
Score trend
Last six months
- Score
- Target residual
Escalation path
Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director
Last reviewed 6 days ago · Outside the engine — below «high»
Project manager
Current levelEng. Youssef Shehabi
Currently followed up here- 2
Programme manager
Eng. Youssef Shehabi
- 3
PMO director
Dr. Reem Al-Qabbani
- 4
Executive Council
Dr. Samer Al-Daqqar
By the PMO director’s decision
Mitigation plan
Each action with its owner and date — tick it off when complete
Early contact with the competent authorities
Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.syIn progressIn 33 days2026-11-30A compliance checklist before every submission
Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.syNot startedIn 33 days2026-11-30
Trigger
A permit application is refused or returned
Contingency
Submit a design alternative that meets the rules