PRJ-2026-006Off track4ExecutionConstructionStalledDelivered by:Ministry of Industry, Internal Trade and Consumer Protection

Sheikh Najjar Industrial City Rehabilitation

Remove from watchlist

Rehabilitating Sheikh Najjar Industrial City’s infrastructure — internal roads, water and drainage networks, power stations and ground improvement on damaged plots — so factories can resume production.

Early warning: ⁦84%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 7.2B

Actual cost

SYP 3.1B

⁦44%⁩ of budget

Progress

⁦39%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 8B

+SYP 883.7M

SPI · CPI

0.78Schedule performance index · 0.780.89Cost performance index · 0.89

Forecast finish

⁦2027-07-04⁩

95 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started

Change request

The change, its impact analysis and the approval decision

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Change request

The change, its impact analysis and the approval decision

Form no.
PSA-PMO-F09
Template edition
3.1
Version
V2
Form date
⁦2026-04-12⁩
ApprovedCR-2026-011Redesign internal roads for heavy trucks

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-006
Project
Sheikh Najjar Industrial City Rehabilitation
Portfolio
Health, Education & Industrial Recovery Portfolio
Sector
Local Development & Governorates Sector
Sponsor
Eng. Bashir Al-Tai
Project manager
Eng. Youssef Shehabi

1The change

TitleAuto-filled
Redesign internal roads for heavy trucks
KindAuto-filled
Scope
Requested byAuto-filled
Eng. Youssef Shehabi
Raised onAuto-filled
⁦2026-04-12⁩

Reason

Returning heavy factories need internal roads with higher axle loads and wider roundabouts the design left out

Justification

Changing it now is cheaper than resurfacing 40 kilometres after opening

2Impact analysis

Cost

+SYP 240M

Schedule

+20 days

Risk

9 → 6

Benefits

+6%

Risk impact

Removes the risk of resurfacing after opening

Benefits impact

40 km of roads ready for heavy trucks from day one

3The approval decision

The PMO’s recommendation

The national PMO recommends approval

Change Committee decision
Approve
Decided on
⁦2026-04-21⁩
Decision number
DEC-2026-033

Approval logChain: Change request approval · version ⁦5⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Youssef ShehabiSenior Project Manager — Governorate ProjectsSubmitted—⁦2026-04-12⁩ 11:56
2Project managerTechnical acceptanceEng. Youssef ShehabiProject managerApproved—⁦2026-04-13⁩ 13:40
3PMO review & impact analysisMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2026-04-15⁩ 14:47
4Financial impactFinancial approvalRasha Al-MudarresFinanceApproved—⁦2026-04-19⁩ 12:15
5Contractual impactFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2026-04-20⁩ 13:52
6Change CommitteeTechnical acceptanceDr. Ziad Al-AtassiChange CommitteeApproved—⁦2026-04-23⁩ 11:08

Signatures

Project manager

Eng. Youssef Shehabi

Approved⁦2026-04-13⁩

PMO review & impact analysis

Mariam Al-Zoubi

Approved⁦2026-04-15⁩

Financial impact

Rasha Al-Mudarres

Approved⁦2026-04-19⁩

Contractual impact

Abdullah Al-Ujaili

Approved⁦2026-04-20⁩

Change Committee

Dr. Ziad Al-Atassi

Approved⁦2026-04-23⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F09 · version V2

Change request

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Change request approval · version ⁦5⁩

Submitted by Eng. Youssef Shehabi on ⁦2026-04-12⁩

  1. Technical acceptance

    Project manager

    Eng. Youssef Shehabi · Project manager

    Approved · ⁦2026-04-13⁩ at ⁦13:40⁩

  2. Methodology review

    PMO review & impact analysis

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2026-04-15⁩ at ⁦14:47⁩

  3. Financial approval

    Financial impact

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2026-04-19⁩ at ⁦12:15⁩

  4. Financial approval

    Contractual impact

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2026-04-20⁩ at ⁦13:52⁩

  5. Technical acceptance

    Change Committee

    Dr. Ziad Al-Atassi · Change Committee

    Approved · ⁦2026-04-23⁩ at ⁦11:08⁩

Steps that do not apply to this record

  • National Projects Steering Committee — the condition «Cost impact above the Change Committee’s authority?» does not holdFrom the authority matrix
  • Authority Executive Council — the condition «Cost impact above the Steering Committee’s authority?» does not holdFrom the authority matrix

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2026-04-21⁩

    Approved by the committee

    Eng. Youssef Shehabi

  2. V1Returned for edit⁦2026-04-12⁩

    The request as raised

    Eng. Youssef Shehabi