Execution
Change request
The change, its impact analysis and the approval decision
- Form no.
- PSA-PMO-F09
- Template edition
- 3.1
- Version
- V2
- Form date
- 2026-04-12
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-006
- Project
- Sheikh Najjar Industrial City Rehabilitation
- Portfolio
- Health, Education & Industrial Recovery Portfolio
- Sector
- Local Development & Governorates Sector
- Sponsor
- Eng. Bashir Al-Tai
- Project manager
- Eng. Youssef Shehabi
1The change
- TitleAuto-filled
- Redesign internal roads for heavy trucks
- KindAuto-filled
- Scope
- Requested byAuto-filled
- Eng. Youssef Shehabi
- Raised onAuto-filled
- 2026-04-12
Reason
Returning heavy factories need internal roads with higher axle loads and wider roundabouts the design left out
Justification
Changing it now is cheaper than resurfacing 40 kilometres after opening
2Impact analysis
Cost
+SYP 240M
Schedule
+20 days
Risk
9 → 6
Benefits
+6%
Risk impact
Removes the risk of resurfacing after opening
Benefits impact
40 km of roads ready for heavy trucks from day one
3The approval decision
The PMO’s recommendation
The national PMO recommends approval
- Change Committee decision
- Approve
- Decided on
- 2026-04-21
- Decision number
- DEC-2026-033
Approval logChain: Change request approval · version 5
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Youssef ShehabiSenior Project Manager — Governorate Projects | Submitted | — | 2026-04-12 11:56 |
| 2 | Project manager | Technical acceptance | Eng. Youssef ShehabiProject manager | Approved | — | 2026-04-13 13:40 |
| 3 | PMO review & impact analysis | Methodology review | Mariam Al-ZoubiPMO — analyst | Approved | — | 2026-04-15 14:47 |
| 4 | Financial impact | Financial approval | Rasha Al-MudarresFinance | Approved | — | 2026-04-19 12:15 |
| 5 | Contractual impact | Financial approval | Abdullah Al-UjailiProcurement & contracts | Approved | — | 2026-04-20 13:52 |
| 6 | Change Committee | Technical acceptance | Dr. Ziad Al-AtassiChange Committee | Approved | — | 2026-04-23 11:08 |
Signatures
Project manager
Eng. Youssef Shehabi
Approved2026-04-13
PMO review & impact analysis
Mariam Al-Zoubi
Approved2026-04-15
Financial impact
Rasha Al-Mudarres
Approved2026-04-19
Contractual impact
Abdullah Al-Ujaili
Approved2026-04-20
Change Committee
Dr. Ziad Al-Atassi
Approved2026-04-23