CR-2026-006Hama National Hospital Upgrade & Extension
Extend the contract by 150 days
Justification and the cost, schedule and risk impact, with a recommendation.
Impact analysis
Before and after — as it will show in the baseline if approved
Cost
—Current budgetSYP 16B
After the changeSYP 16B
0.0%
Schedule
+150 d- Baseline finish2026-12-31
- New finish2027-05-30
Risk
−4Eases schedule pressure but adds indirect cost
Benefits
−6%Patients move into the new wards five months later and the temporary wards run on
-6% of expected benefits
Reason for change
Accumulated façade and MEP delays
Justification
A realistic extension allows an achievable baseline instead of open-ended delay
PMO recommendation
DeferThe change control board deferred the decision pending the independent engineer’s report
Approval workflow
Submitted
Eng. Sara Al-Barazi
Done2026-10-01
PM review
Eng. Sara Al-Barazi
Done2026-10-02
Impact analysis
Kinan Azzam
Done2026-10-06
- 4
Change committee recommendation
Dr. Ziad Al-Atassi
Now2026-10-29
- 5
Executive Council decision
Dr. Samer Al-Daqqar
Later
- 6
Baseline updated
Eng. Sara Al-Barazi
Later
Why this route
The route is built from the request’s kind and impact level under the approved authority matrix.
Impact levelMajorAbove SYP 125M or 90 days
- A schedule impact of 150 days is above 90 days — «major»: the Change Committee recommends and the Executive Council decides.
Change committee vote
Members vote before or during the meeting; the decision is taken once quorum is met
- Dr. Ziad Al-AtassiDeputy President, Strategy & PerformanceDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.syChairNot voted
- Dr. Reem Al-QabbaniDirector, National Project Management OfficeDr. Reem Al-QabbaniDirector, National Project Management OfficeP-002reem.alqabbani@psa.gov.syYouNot voted
- Omar Al-NahhasSenior Finance & Contracts SpecialistOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.syNot voted
- Rasha Al-MudarresDirector General, Finance & ContractsRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.syNot voted
- Eng. Rita GhanemEnterprise ArchitectEng. Rita GhanemEnterprise ArchitectP-031rita.ghanem@psa.gov.syNot voted
- Eng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syNot voted
- Approve0
- Approve with conditions0
- Reject0
- Abstain0
4 short of quorum · Awaiting the change committee’s decision in meeting 42