CR-2026-006Hama National Hospital Upgrade & Extension

Extend the contract by 150 days

ScheduleIn reviewImpact level: Major6 days overdue2026-10-22

Justification and the cost, schedule and risk impact, with a recommendation.

Electronic form

Impact analysis

Before and after — as it will show in the baseline if approved

Cost

—

Current budgetSYP 16B

After the changeSYP 16B

0.0%

Schedule

+⁦150⁩ d
  • Baseline finish2026-12-31
  • New finish2027-05-30

Risk

−4
16High12Medium
Risk RSK-0027 · Late delivery of operating-theatre equipment from the overseas supplier

Eases schedule pressure but adds indirect cost

Benefits

−6%

Patients move into the new wards five months later and the temporary wards run on

⁦-6⁩% of expected benefits

Reason for change

Accumulated façade and MEP delays

Justification

A realistic extension allows an achievable baseline instead of open-ended delay

PMO recommendation

Defer

The change control board deferred the decision pending the independent engineer’s report

Approval workflow

  1. Submitted

    Eng. Sara Al-Barazi

    Done2026-10-01

  2. PM review

    Eng. Sara Al-Barazi

    Done2026-10-02

  3. Impact analysis

    Kinan Azzam

    Done2026-10-06

  4. 4

    Change committee recommendation

    Dr. Ziad Al-Atassi

    Now2026-10-29

  5. 5

    Executive Council decision

    Dr. Samer Al-Daqqar

    Later

  6. 6

    Baseline updated

    Eng. Sara Al-Barazi

    Later

Why this route

The route is built from the request’s kind and impact level under the approved authority matrix.

Impact levelMajorAbove SYP 125M or 90 days

  • A schedule impact of 150 days is above 90 days — «major»: the Change Committee recommends and the Executive Council decides.

Change committee vote

Members vote before or during the meeting; the decision is taken once quorum is met

Change Committee — meeting 4229 October 2026 13:00Meeting room 3 — fifth floor
  • Dr. Ziad Al-AtassiDeputy President, Strategy & PerformanceDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.syChairNot voted
  • Dr. Reem Al-QabbaniDirector, National Project Management OfficeDr. Reem Al-QabbaniDirector, National Project Management OfficeP-002reem.alqabbani@psa.gov.syYouNot voted
  • Omar Al-NahhasSenior Finance & Contracts SpecialistOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.syNot voted
  • Rasha Al-MudarresDirector General, Finance & ContractsRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.syNot voted
  • Eng. Rita GhanemEnterprise ArchitectEng. Rita GhanemEnterprise ArchitectP-031rita.ghanem@psa.gov.syNot voted
  • Eng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syNot voted
0/6⁦4⁩ short of quorum
  • Approve0
  • Approve with conditions0
  • Reject0
  • Abstain0

⁦4⁩ short of quorum · Awaiting the change committee’s decision in meeting ⁦42⁩