Execution
Change request
The change, its impact analysis and the approval decision
- Form no.
- PSA-PMO-F09
- Template edition
- 3.1
- Version
- V1
- Form date
- 2026-10-01
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-007
- Project
- Hama National Hospital Upgrade & Extension
- Portfolio
- Health, Education & Industrial Recovery Portfolio
- Sector
- Development Projects Follow-up Sector
- Sponsor
- Eng. Abdulrahman Al-Kilani
- Project manager
- Eng. Sara Al-Barazi
1The change
- TitleAuto-filled
- Extend the contract by 150 days
- KindAuto-filled
- Schedule
- Requested byAuto-filled
- Eng. Sara Al-Barazi
- Raised onAuto-filled
- 2026-10-01
Reason
Accumulated façade and MEP delays
Justification
A realistic extension allows an achievable baseline instead of open-ended delay
2Impact analysis
Cost
SYP 0
Schedule
+150 days
Risk
16 → 12
Benefits
-6%
Risk impact
Eases schedule pressure but adds indirect cost
Benefits impact
Patients move into the new wards five months later and the temporary wards run on
3The approval decision
The PMO’s recommendation
The change control board deferred the decision pending the independent engineer’s report
- Change Committee decision
- Not taken yet
- Decided on
- —
- Decision number
- —
Approval logChain: Change request approval · version 5
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Sara Al-BaraziSenior Project Manager — Hospitals & Health Facilities | Submitted | — | 2026-10-01 09:54 |
| 2 | Project manager | Technical acceptance | Eng. Sara Al-BaraziProject manager | Approved | — | 2026-10-04 11:38 |
| 3 | PMO review & impact analysis | Methodology review | Mariam Al-ZoubiPMO — analyst | Approved | — | 2026-10-06 12:45 |
| 4 | Change Committee | Technical acceptance | Approval engineChange Committee | Pre-breach alert | — | 2026-10-11 08:00 |
| 5 | Change Committee | Technical acceptance | Approval engineEscalated automatically to Senior management (Dr. Samer Al-Daqqar) on 2026-10-13 | Automatic escalation | — | 2026-10-13 08:05 |
Signatures
Project manager
Eng. Sara Al-Barazi
Approved2026-10-04
PMO review & impact analysis
Mariam Al-Zoubi
Approved2026-10-06
Change Committee
Dr. Ziad Al-Atassi
Awaiting decision