Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-007Critical4ExecutionConstructionStalledDelivered by:Ministry of Health

Hama National Hospital Upgrade & Extension

Remove from watchlist

Extending Hama National Hospital with a new wing of 42 wards and theatres and upgrading its medical equipment, running 9 temporary wards so care never stops during the works.

Early warning: ⁦97%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SYP 16B

Actual cost

SYP 11.1B

⁦70%⁩ of budget

Progress

⁦57%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 19.5B

+SYP 3.5B

SPI · CPI

0.70Schedule performance index · 0.700.82Cost performance index · 0.82

Forecast finish

⁦2027-06-01⁩

152 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure7 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate23 July 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate7 October 2026Closure · Not startedClosure · Not started

Change request

The change, its impact analysis and the approval decision

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Change request

The change, its impact analysis and the approval decision

Form no.
PSA-PMO-F09
Template edition
3.1
Version
V1
Form date
⁦2026-10-01⁩
In approvalCR-2026-006Extend the contract by 150 days

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-007
Project
Hama National Hospital Upgrade & Extension
Portfolio
Health, Education & Industrial Recovery Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Eng. Abdulrahman Al-Kilani
Project manager
Eng. Sara Al-Barazi

1The change

TitleAuto-filled
Extend the contract by 150 days
KindAuto-filled
Schedule
Requested byAuto-filled
Eng. Sara Al-Barazi
Raised onAuto-filled
⁦2026-10-01⁩

Reason

Accumulated façade and MEP delays

Justification

A realistic extension allows an achievable baseline instead of open-ended delay

2Impact analysis

Cost

SYP 0

Schedule

+150 days

Risk

16 → 12

Benefits

-6%

Risk impact

Eases schedule pressure but adds indirect cost

Benefits impact

Patients move into the new wards five months later and the temporary wards run on

3The approval decision

The PMO’s recommendation

The change control board deferred the decision pending the independent engineer’s report

Change Committee decision
Not taken yet
Decided on
—
Decision number
—

Approval logChain: Change request approval · version ⁦5⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesSubmitted—⁦2026-10-01⁩ 09:54
2Project managerTechnical acceptanceEng. Sara Al-BaraziProject managerApproved—⁦2026-10-04⁩ 11:38
3PMO review & impact analysisMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2026-10-06⁩ 12:45
4Change CommitteeTechnical acceptanceApproval engineChange CommitteePre-breach alert—⁦2026-10-11⁩ 08:00
5Change CommitteeTechnical acceptanceApproval engineEscalated automatically to Senior management (Dr. Samer Al-Daqqar) on ⁦2026-10-13⁩Automatic escalation—⁦2026-10-13⁩ 08:05

Signatures

Project manager

Eng. Sara Al-Barazi

Approved⁦2026-10-04⁩

PMO review & impact analysis

Mariam Al-Zoubi

Approved⁦2026-10-06⁩

Change Committee

Dr. Ziad Al-Atassi

Awaiting decision

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F09 · version V1

Change request

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Change request approval · version ⁦5⁩

Submitted by Eng. Sara Al-Barazi on ⁦2026-10-01⁩

  1. Technical acceptance

    Project manager

    Eng. Sara Al-Barazi · Project manager

    Approved · ⁦2026-10-04⁩ at ⁦11:38⁩

  2. Methodology review

    PMO review & impact analysis

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2026-10-06⁩ at ⁦12:45⁩

  3. Technical acceptance

    Change Committee

    Dr. Ziad Al-Atassi · Change Committee

    Delegated to Dr. Reem Al-Qabbani

    13 working days overdueAction time limit exceeded · Limit 3 working daysLimit 3 working days · Due ⁦2026-10-11⁩

    Pre-breach alert at ⁦75%⁩ — sent ⁦2026-10-11⁩

    Escalated automatically to Senior management (Dr. Samer Al-Daqqar) on ⁦2026-10-13⁩

Steps that do not apply to this record

  • Financial impact — the condition «Financial link?» does not hold
  • Contractual impact — the condition «Contract link?» does not hold
  • National Projects Steering Committee — the condition «Cost impact above the Change Committee’s authority?» does not holdFrom the authority matrix
  • Authority Executive Council — the condition «Cost impact above the Steering Committee’s authority?» does not holdFrom the authority matrix

Previous versions

Every version is kept with its status and what changed.

  1. V1In approvalCurrent⁦2026-10-01⁩

    The request as raised

    Eng. Sara Al-Barazi

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close