Hama National Hospital Upgrade & Extension
Remove from watchlistExtending Hama National Hospital with a new wing of 42 wards and theatres and upgrading its medical equipment, running 9 temporary wards so care never stops during the works.
Budget (BAC)
Actual cost
70% of budget
Progress
Estimate at completion
+SYP 3.5B
SPI · CPI
Forecast finish
152 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure7 October 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate23 July 2024Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate7 October 2026Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2024-09-10 | 2025-01-10 | +122 days | Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-02-25 | 2025-09-29 | +216 days | Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2025-11-05 | 2026-10-26 | +355 days | Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-07-16 | 2027-04-15 | +273 days | Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy | Late | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2026-12-31 | 2027-06-02 | +153 days | Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
57%Awaiting acceptance
10%Not handed in
33%Deliverable flow
Display options
| Project plan & baseline007-D1 | 3% | CRT-007-01 | Approved | Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy | Eng. Fadi Al-Droubi | 2024-06-18 | V1 | 3 of 3 |
| Monitoring & reporting007-D2 | 3% | CRT-007-02 | Approved | Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.sy | Eng. Fadi Al-Droubi | 2024-09-10 | V1 | 3 of 3 |
| Detailed design007-D3 | 6% | CRT-007-03 | Approved | Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.sy | Eng. Fadi Al-Droubi | 2024-12-03 | V1 | 3 of 3 |
| Permits & approvals007-D4 | 6% | CRT-007-04 | Approved | Eng. Abdulrahman Al-KilaniEng. Abdulrahman Al-KilaniDeputy President, Development Projects Follow-upP-010abdulrahman.alkilani@psa.gov.sy | Eng. Fadi Al-Droubi | 2025-02-25 | V1 | 3 of 3 |
| Site works & excavation007-D5 | 13% | CRT-007-05 | Approved | Eng. Abdulrahman Al-KilaniEng. Abdulrahman Al-KilaniDeputy President, Development Projects Follow-upP-010abdulrahman.alkilani@psa.gov.sy | Eng. Fadi Al-Droubi | 2025-05-21 | V1 | 3 of 3 |
| Structure007-D6 | 13% | CRT-007-06 | Approved | Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy | Eng. Fadi Al-Droubi | 2025-08-13 | V1 | 3 of 3 |
| Finishes007-D7 | 13% | CRT-007-07 | Approved | Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.sy | Eng. Fadi Al-Droubi | 2025-11-05 | V1 | 3 of 3 |
| Supply007-D8 | 10% | — | Submitted | Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy | Eng. Fadi Al-Droubi | 2026-01-28 | V1 | 1 of 3 |
| Installation007-D9 | 10% | — | Draft | Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.sy | Eng. Fadi Al-Droubi | 2026-04-22 | V0 | 0 of 3 |
| Testing & commissioning007-D10 | 9% | — | Draft | Eng. Abdulrahman Al-KilaniEng. Abdulrahman Al-KilaniDeputy President, Development Projects Follow-upP-010abdulrahman.alkilani@psa.gov.sy | Eng. Fadi Al-Droubi | 2026-07-16 | V0 | 0 of 3 |
| Provisional acceptance007-D11 | 7% | — | Draft | Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.sy | Eng. Fadi Al-Droubi | 2026-10-08 | V0 | 0 of 3 |
| Final acceptance007-D12 | 7% | — | Draft | Eng. Abdulrahman Al-KilaniEng. Abdulrahman Al-KilaniDeputy President, Development Projects Follow-upP-010abdulrahman.alkilani@psa.gov.sy | Eng. Fadi Al-Droubi | 2026-12-31 | V0 | 0 of 3 |
| Total · 12 | 100% |