PRJ-2026-007Critical4ExecutionConstructionStalledDelivered by:Ministry of Health

Hama National Hospital Upgrade & Extension

Remove from watchlist

Extending Hama National Hospital with a new wing of 42 wards and theatres and upgrading its medical equipment, running 9 temporary wards so care never stops during the works.

Early warning: ⁦97%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SYP 16B

Actual cost

SYP 11.1B

⁦70%⁩ of budget

Progress

⁦57%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 19.5B

+SYP 3.5B

SPI · CPI

0.70Schedule performance index · 0.700.82Cost performance index · 0.82

Forecast finish

⁦2027-06-01⁩

152 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure7 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate23 July 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate7 October 2026Closure · Not startedClosure · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2026-12-31⁩
    Budget
    SYP 16B
    ⁦17⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2024-02-04⁩ · by Eng. Abdulrahman Al-Kilani

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2027-06-02⁩
    ⁦+153⁩ days
    Budget
    SYP 16B
    ⁦17⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Eng. Sara Al-Barazi

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2026-12-31⁩⁦2027-06-02⁩

⁦+153⁩ days

Budget

SYP 16BSYP 16B

⁦0.00⁩ SYP M

Milestones moved

5 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2025-012025-072026-012026-072027-01
  • Project plan approved⁦+122⁩
  • Designs approved⁦+216⁩
  • Build complete⁦+355⁩
  • Testing & acceptance complete⁦+273⁩
  • Final handover⁦+153⁩

Version AVersion B

Cost by WBS element

Difference in SYP millions from A to B

  • 1Management & governance⁦+239.53⁩
  • 2Design & permits⁦+479.06⁩
  • 3Civil works⁦+1,837.03⁩
  • 4MEP works⁦+1,019.83⁩
  • 5Handover⁦+496.74⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Eng. Sara Al-Barazi
  2. Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.⁦2024-02-04⁩by Eng. Abdulrahman Al-Kilani