CR-2026-013Government Backup Data Centre, Homs — Phase 2

Replace the cooling-unit supplier

ContractApprovedImpact level: Moderate

Justification and the cost, schedule and risk impact, with a recommendation.

Electronic form

Impact analysis

Before and after — as it will show in the baseline if approved

Cost

+SYP 77.5M

Current budgetSYP 3.6B

After the changeSYP 3.7B

+2.1%

Schedule

+⁦14⁩ d
  • Baseline finish2026-11-16
  • New finish2026-11-30

Risk

−4

Benefits

+2%

8% better energy efficiency

⁦+2⁩% of expected benefits

Reason for change

The original cooling supplier defaulted

Justification

The alternative delivers in 14 weeks with a longer warranty

PMO recommendation

Approve

The national PMO recommends approval

Approval workflow

  1. Submitted

    Eng. George Haddad

    Done2026-05-17

  2. PM review

    Eng. George Haddad

    Done2026-05-18

  3. Impact analysis

    Kinan Azzam

    Done2026-05-22

  4. Finance & procurement

    Rasha Al-Mudarres

    Done2026-05-23

  5. Change committee decision

    Dr. Ziad Al-Atassi

    Done2026-05-28

  6. Baseline updated

    Eng. George Haddad

    Done2026-06-01

Why this route

The route is built from the request’s kind and impact level under the approved authority matrix.

Impact levelModerateUp to SYP 125M and 90 days

  • Impact SYP 77.5M and 14 days — «moderate», so the Change Committee decides.
  • It touches a signed contract, so Finance & Procurement review it contractually.

Change committee vote

Members vote before or during the meeting; the decision is taken once quorum is met

  • Dr. Ziad Al-AtassiDeputy President, Strategy & PerformanceDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.syChairApprove
  • Dr. Reem Al-QabbaniDirector, National Project Management OfficeDr. Reem Al-QabbaniDirector, National Project Management OfficeP-002reem.alqabbani@psa.gov.syYouApprove
  • Omar Al-NahhasSenior Finance & Contracts SpecialistOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.syApprove
  • Rasha Al-MudarresDirector General, Finance & ContractsRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.syApprove
  • Eng. Rita GhanemEnterprise ArchitectEng. Rita GhanemEnterprise ArchitectP-031rita.ghanem@psa.gov.syApprove
  • Eng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syApprove
6/6Quorum met
  • Approve6
  • Approve with conditions0
  • Reject0
  • Abstain0

Decided by the committee on 28 May 2026The decision in the log · DEC-2026-014

Baseline

Baseline updated on 1 June 2026