CR-2026-013Government Backup Data Centre, Homs — Phase 2
Replace the cooling-unit supplier
Justification and the cost, schedule and risk impact, with a recommendation.
Impact analysis
Before and after — as it will show in the baseline if approved
Cost
+SYP 77.5MCurrent budgetSYP 3.6B
After the changeSYP 3.7B
+2.1%
Schedule
+14 d- Baseline finish2026-11-16
- New finish2026-11-30
Risk
−4Lowers the late-supply risk
Benefits
+2%8% better energy efficiency
+2% of expected benefits
Reason for change
The original cooling supplier defaulted
Justification
The alternative delivers in 14 weeks with a longer warranty
PMO recommendation
ApproveThe national PMO recommends approval
Approval workflow
Submitted
Eng. George Haddad
Done2026-05-17
PM review
Eng. George Haddad
Done2026-05-18
Impact analysis
Kinan Azzam
Done2026-05-22
Finance & procurement
Rasha Al-Mudarres
Done2026-05-23
Change committee decision
Dr. Ziad Al-Atassi
Done2026-05-28
Baseline updated
Eng. George Haddad
Done2026-06-01
Why this route
The route is built from the request’s kind and impact level under the approved authority matrix.
Impact levelModerateUp to SYP 125M and 90 days
- Impact SYP 77.5M and 14 days — «moderate», so the Change Committee decides.
- It touches a signed contract, so Finance & Procurement review it contractually.
Change committee vote
Members vote before or during the meeting; the decision is taken once quorum is met
- Dr. Ziad Al-AtassiDeputy President, Strategy & PerformanceDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.syChairApprove
- Dr. Reem Al-QabbaniDirector, National Project Management OfficeDr. Reem Al-QabbaniDirector, National Project Management OfficeP-002reem.alqabbani@psa.gov.syYouApprove
- Omar Al-NahhasSenior Finance & Contracts SpecialistOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.syApprove
- Rasha Al-MudarresDirector General, Finance & ContractsRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.syApprove
- Eng. Rita GhanemEnterprise ArchitectEng. Rita GhanemEnterprise ArchitectP-031rita.ghanem@psa.gov.syApprove
- Eng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syApprove
- Approve6
- Approve with conditions0
- Reject0
- Abstain0
Decided by the committee on 28 May 2026The decision in the log · DEC-2026-014
Baseline
Baseline updated on 1 June 2026