RSK-0020Government Backup Data Centre, Homs — Phase 2

Late delivery of cooling units and standby generators

12MediumOpen

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Overlapping critical activities that depend on outside supplies and approvals

Preventive controls

  • Re-sequence critical activities and refresh the critical path
  • Weekly supply follow-up with the vendor or contractor

2 / 2

Event

Late delivery of cooling units and standby generators

12MediumTrigger

SPI under 0.85 two months running

Contingency

Extra shifts and fast-tracking the remaining works

Impact

Key milestones slip and indirect costs rise

SYP 80M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
12Medium

Residual

5
4
3
2
1
1
2
3
4
5
4Low

Exposure

SYP 80M

Residual

⁦67⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 7 days ago · Outside the engine — below «high»

  1. Project manager

    Current level

    Eng. George Haddad

    Currently followed up here
  2. 2

    Programme manager

    Eng. George Haddad

  3. 3

    PMO director

    Dr. Reem Al-Qabbani

  4. 4

    Executive Council

    Dr. Samer Al-Daqqar

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦0⁩ of ⁦2⁩ done
  • Re-sequence critical activities and refresh the critical path

    Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy
    In progressIn 33 days2026-11-30
  • Weekly supply follow-up with the vendor or contractor

    Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy
    Not startedIn 33 days2026-11-30

Trigger

SPI under 0.85 two months running

Contingency

Extra shifts and fast-tracking the remaining works

Esc