PRJ-2026-003At risk4ExecutionWaterfallIn progressDelivered by:Ministry of Communications and Information Technology

Government Backup Data Centre, Homs — Phase 2

Add to watchlist

A Tier III standby site in Homs, away from the capital, that keeps the government e-services platform and the ministries’ systems running after a major outage at the main Damascus data centre.

Early warning: ⁦63%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 3.7B

Actual cost

SYP 2.9B

⁦79%⁩ of budget

Progress

⁦72%⁩Awaiting acceptance ⁦8%⁩

Estimate at completion

SYP 4.1B

+SYP 365.9M

SPI · CPI

0.90Schedule performance index · 0.900.91Cost performance index · 0.91

Forecast finish

⁦2027-01-07⁩

38 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 February 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate6 April 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate11 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 October 2026Closure · Not startedClosure · Not started

Change request

The change, its impact analysis and the approval decision

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Change request

The change, its impact analysis and the approval decision

Form no.
PSA-PMO-F09
Template edition
3.1
Version
V2
Form date
⁦2026-05-17⁩
ApprovedCR-2026-013Replace the cooling-unit supplier

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-003
Project
Government Backup Data Centre, Homs — Phase 2
Portfolio
Government Digital Infrastructure & Systems Portfolio
Sector
Digital Transformation Sector
Sponsor
Eng. Khaled Al-Kayyali
Project manager
Eng. George Haddad

1The change

TitleAuto-filled
Replace the cooling-unit supplier
KindAuto-filled
Contract
Requested byAuto-filled
Eng. George Haddad
Raised onAuto-filled
⁦2026-05-17⁩

Reason

The original cooling supplier defaulted

Justification

The alternative delivers in 14 weeks with a longer warranty

2Impact analysis

Cost

+SYP 77.5M

Schedule

+14 days

Risk

16 → 12

Benefits

+2%

Risk impact

Lowers the late-supply risk

Benefits impact

8% better energy efficiency

3The approval decision

The PMO’s recommendation

The national PMO recommends approval

Change Committee decision
Approve
Decided on
⁦2026-05-28⁩
Decision number
DEC-2026-014

Approval logChain: Change request approval · version ⁦5⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. George HaddadDirector, Data Centres & Government NetworkSubmitted—⁦2026-05-17⁩ 13:10
2Project managerTechnical acceptanceEng. George HaddadProject managerApproved—⁦2026-05-18⁩ 09:54
3PMO review & impact analysisMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2026-05-20⁩ 10:01
4Financial impactFinancial approvalRasha Al-MudarresFinanceApproved—⁦2026-05-24⁩ 14:29
5Contractual impactFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2026-05-25⁩ 09:06
6Change CommitteeTechnical acceptanceDr. Ziad Al-AtassiChange CommitteeApproved—⁦2026-05-31⁩ 13:22

Signatures

Project manager

Eng. George Haddad

Approved⁦2026-05-18⁩

PMO review & impact analysis

Mariam Al-Zoubi

Approved⁦2026-05-20⁩

Financial impact

Rasha Al-Mudarres

Approved⁦2026-05-24⁩

Contractual impact

Abdullah Al-Ujaili

Approved⁦2026-05-25⁩

Change Committee

Dr. Ziad Al-Atassi

Approved⁦2026-05-31⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F09 · version V2

Change request

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Change request approval · version ⁦5⁩

Submitted by Eng. George Haddad on ⁦2026-05-17⁩

  1. Technical acceptance

    Project manager

    Eng. George Haddad · Project manager

    Approved · ⁦2026-05-18⁩ at ⁦09:54⁩

  2. Methodology review

    PMO review & impact analysis

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2026-05-20⁩ at ⁦10:01⁩

  3. Financial approval

    Financial impact

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2026-05-24⁩ at ⁦14:29⁩

  4. Financial approval

    Contractual impact

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2026-05-25⁩ at ⁦09:06⁩

  5. Technical acceptance

    Change Committee

    Dr. Ziad Al-Atassi · Change Committee

    Approved · ⁦2026-05-31⁩ at ⁦13:22⁩

Steps that do not apply to this record

  • National Projects Steering Committee — the condition «Cost impact above the Change Committee’s authority?» does not holdFrom the authority matrix
  • Authority Executive Council — the condition «Cost impact above the Steering Committee’s authority?» does not holdFrom the authority matrix

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2026-05-28⁩

    Approved by the committee

    Eng. George Haddad

  2. V1Returned for edit⁦2026-05-17⁩

    The request as raised

    Eng. George Haddad