Late backup-centre equipment delays the migration window
PRK-03-1·Mitigate·Eng. George Haddad
Programme · PG-03 · Government Digital Infrastructure & Systems Portfolio
The Homs backup data centre, the government cloud and the cybersecurity programme.
incl. SYP 150M programme reserve
72% of budget
Estimate at completion
Planned 73%
Cost performance index 0.94
Manager
Eng. George Haddad
Director, Data Centres & Government Network
Sponsor
Eng. Mazen Kassab
Director General, Government Digital Infrastructure
Projects
3 projects
2025-02-02 — 2027-03-21
On track 1At risk 2
What the programme must achieve, and the strategic objectives it serves.
Host 50% of ministry systems on the government cloud inside Syria
A backup centre in Homs for critical government systems with a recovery time under 4 hours
95% compliance with the national cybersecurity controls
Serves strategic objectives
From baseline to target
Systems hosted on the government cloud
by 2027National controls compliance
by 2026One lane per project: start to forecast finish, with the progress earned and the baseline finish.
What waits on what. Red links are on the programme’s critical path.
Critical path
Critical
Migration needs the backup centre ready before the critical systems move
Security controls are applied to the cloud tenancy before migration
Risks that hit more than one project, managed at programme level.
Late backup-centre equipment delays the migration window
PRK-03-1·Mitigate·Eng. George Haddad
4 risks
Impact
| Probability \ Impact | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 0 · Low | 0 · Medium | 0 · High | 0 · Critical | 0 · Critical |
| 4 | 0 · Low | 0 · Medium | 1 · Medium | 1 · High | 0 · Critical |
| 3 | 0 · Low | 0 · Low | 1 · Medium | 0 · Medium | 0 · High |
| 2 | 0 · Low | 0 · Low | 0 · Low | 0 · Medium | 1 · Medium |
| 1 | 0 · Low | 0 · Low | 0 · Low | 0 · Low | 0 · Low |
Ministry systems hosted on the government cloud
47%
+2
Target 50%94%
Compliance with the national cybersecurity controls
91%
+1
Target 95%96%
Power against interest; click a person to see their role.
Keep satisfied1
Manage closely3
Monitor0
Keep informed0
Interest
What the committees decided on the programme’s projects, and what the programme raised to them.
Committees
Monthly · Quorum 5
Members
6 members
As needed · Quorum 3
The programme’s performance is computed from these projects.
Display options
| Manager | ||||||||
|---|---|---|---|---|---|---|---|---|
| Government Backup Data Centre, Homs — Phase 2PRJ-2026-003 | Eng. George Haddad | 4Execution | At risk | 72% | SYP3.7B | SYP4.1B+9.9% | 0.90Schedule performance index · 0.90 | 0.91Cost performance index · 0.91 |
| Government Network Cybersecurity ProgrammePRJ-2026-005 | Eng. Hussam Zeidan | 4Execution | On track | 88% | SYP965M | SYP936.9M−2.9% | 1.02Schedule performance index · 1.02 | 1.03Cost performance index · 1.03 |
| Government Cloud & Ministry Systems MigrationPRJ-2026-009 | Eng. George Haddad | 4Execution | At risk | 47% | SYP1.3B | SYP1.3B+3.1% | 0.89Schedule performance index · 0.89 | 0.97Cost performance index · 0.97 |
| Total · 3 | SYP6B | SYP6.3B |
SYP 6B
Budget
| Category | Value | Share |
|---|---|---|
| Government Backup Data Centre, Homs — Phase 2 | SYP 3.7B | 62% |
| Government Network Cybersecurity Programme | SYP 965M | 16% |
| Government Cloud & Ministry Systems Migration | SYP 1.3B | 22% |
| Total | SYP 6B | 100% |