Programme · PG-03 · Government Digital Infrastructure & Systems Portfolio

Digital Infrastructure & Cybersecurity Programme

At risk

The Homs backup data centre, the government cloud and the cybersecurity programme.

Approved budget
SYP 6.1B

incl. SYP 150M programme reserve

Actual spend
SYP 4.4B

⁦72%⁩ of budget

EAC
SYP 6.3B+6.3%

Estimate at completion

Progress
⁦69%⁩

Planned ⁦73%⁩

Schedule performance index
0.92

Cost performance index 0.94

Manager

Eng. George Haddad

Director, Data Centres & Government Network

Sponsor

Eng. Mazen Kassab

Director General, Government Digital Infrastructure

Projects

3 projects

2025-02-02 — 2027-03-21

On track 1At risk 2

Programme objectives

What the programme must achieve, and the strategic objectives it serves.

  1. 1

    Host 50% of ministry systems on the government cloud inside Syria

  2. 2

    A backup centre in Homs for critical government systems with a recovery time under 4 hours

  3. 3

    95% compliance with the national cybersecurity controls

Programme benefits

From baseline to target

  • Systems hosted on the government cloud

    by ⁦2027⁩
    Baseline 20Current 47 %Target 50
  • National controls compliance

    by ⁦2026⁩
    Baseline 78Current 91 %Target 95

Roadmap

One lane per project: start to forecast finish, with the progress earned and the baseline finish.

EarnedRemainingBaseline finishSlip
202520262027
2026-12-10
2027-01-07
2027-03-21

Dependencies between projects

What waits on what. Red links are on the programme’s critical path.

Critical path

What each project needs from the one before

  • Critical

    Migration needs the backup centre ready before the critical systems move

  • Security controls are applied to the cloud tenancy before migration

Shared risks

Risks that hit more than one project, managed at programme level.

12

Late backup-centre equipment delays the migration window

PRK-03-1·Mitigate·Eng. George Haddad

Affects

Open risks in the programme’s projects

4 risks

Open risks in the programme’s projects
  • Critical0
  • High1
  • Medium3
  • Low0
  • Risks 4
Probability
5
4
3
2
1
12345

Impact

Open risks in the programme’s projects
Probability \ Impact12345
50 · Low0 · Medium0 · High0 · Critical0 · Critical
40 · Low0 · Medium1 · Medium1 · High0 · Critical
30 · Low0 · Low1 · Medium0 · Medium0 · High
20 · Low0 · Low0 · Low0 · Medium1 · Medium
10 · Low0 · Low0 · Low0 · Low0 · Low

Programme KPIs · Stakeholders

Stakeholders

Power against interest; click a person to see their role.

Power

Keep satisfied1

Manage closely3

Monitor0

Keep informed0

Eng. Mazen KassabManage closelyEng. Hussam ZeidanManage closelyNour Al-JabiriManage closelyRasha Al-MudarresKeep satisfied

Interest

Programme decisions

What the committees decided on the programme’s projects, and what the programme raised to them.

    Committees

    National Projects Steering Committee

    Monthly · Quorum ⁦5⁩

    Dr. Ziad Al-Atassi · Deputy President, Strategy & PerformanceEng. Abdulrahman Al-Kilani · Deputy President, Development Projects Follow-upEng. Khaled Al-Kayyali · Deputy President, Digital Transformation
    Chair: Dr. Samer Al-DaqqarNext meeting 2026-11-03
    Bid Opening & Award Committee

    As needed · Quorum ⁦3⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistAbdullah Al-Ujaili · Contracts & Tendering SpecialistEng. Wael Al-Khawlani · Director, Engineering Supervision of Construction ProjectsEng. Rita Ghanem · Enterprise Architect
    Chair: Rasha Al-MudarresNo meeting scheduled

    Programme projects

    The programme’s performance is computed from these projects.

    ⁦3⁩ results
    Export CSV
    Manager
    Government Backup Data Centre, Homs — Phase 2PRJ-2026-003Eng. George Haddad4ExecutionAt risk⁦72%⁩SYP3.7BSYP4.1B⁦+9.9%⁩0.90Schedule performance index · 0.900.91Cost performance index · 0.91
    Government Network Cybersecurity ProgrammePRJ-2026-005Eng. Hussam Zeidan4ExecutionOn track⁦88%⁩SYP965MSYP936.9M⁦−2.9%⁩1.02Schedule performance index · 1.021.03Cost performance index · 1.03
    Government Cloud & Ministry Systems MigrationPRJ-2026-009Eng. George Haddad4ExecutionAt risk⁦47%⁩SYP1.3BSYP1.3B⁦+3.1%⁩0.89Schedule performance index · 0.890.97Cost performance index · 0.97
    Total · 3SYP6BSYP6.3B
    ⁦1⁩–⁦3⁩ of ⁦3⁩

    Budget shares

    Budget shares

    SYP 6B

    Budget

    • Government Backup Data Centre, Homs — Phase 2SYP 3.7B⁦62%⁩
    • Government Network Cybersecurity ProgrammeSYP 965M⁦16%⁩
    • Government Cloud & Ministry Systems MigrationSYP 1.3B⁦22%⁩
    Budget shares
    CategoryValueShare
    Government Backup Data Centre, Homs — Phase 2SYP 3.7B⁦62%⁩
    Government Network Cybersecurity ProgrammeSYP 965M⁦16%⁩
    Government Cloud & Ministry Systems MigrationSYP 1.3B⁦22%⁩
    TotalSYP 6B⁦100%⁩