PRJ-2026-003At risk4ExecutionWaterfallIn progressDelivered by:Ministry of Communications and Information Technology

Government Backup Data Centre, Homs — Phase 2

Add to watchlist

A Tier III standby site in Homs, away from the capital, that keeps the government e-services platform and the ministries’ systems running after a major outage at the main Damascus data centre.

Early warning: ⁦63%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 3.7B

Actual cost

SYP 2.9B

⁦79%⁩ of budget

Progress

⁦72%⁩Awaiting acceptance ⁦8%⁩

Estimate at completion

SYP 4.1B

+SYP 365.9M

SPI · CPI

0.90Schedule performance index · 0.900.91Cost performance index · 0.91

Forecast finish

⁦2027-01-07⁩

38 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 February 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate6 April 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate11 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 October 2026Closure · Not startedClosure · Not started
Fields required by the project’s stage (Execution): 15 fields required now.Field settings

Planning and Statistics Authority

Project charter

Government Backup Data Centre, Homs — Phase 2

APPROVEDV2Approved ⁦2025-04-04⁩

1Project identity

Required at this stage
Project name
Government Backup Data Centre, Homs — Phase 2
Project code
PRJ-2026-003
Project sponsor
Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy
Project manager
Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy
Project owner
Eng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.sy
Portfolio & programme
Government Digital Infrastructure & Systems PortfolioDigital Infrastructure & Cybersecurity Programme
Type & methodology
IT · Waterfall
Current phase
4Execution

2Background & rationale

Required at this stage

A Tier III standby site in Homs, away from the capital, that keeps the government e-services platform and the ministries’ systems running after a major outage at the main Damascus data centre.

3Objectives

Required at this stage
  1. 1Sound governance and effective follow-up of projects and data

4Scope

Required at this stage

In scope

  • A Tier III standby site in Homs, away from the capital, that keeps the government e-services platform and the ministries’ systems running after a major outage at the main Damascus data centre.
  • Migration from legacy systems
  • ERP integration

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Migration from legacy systems
  2. 2ERP integration
  3. 3National cybersecurity controls

6Deliverables

Required at this stage
1Project management plan⁦2025-04-30⁩
2Main deliverable — stage 1⁦2026-02-08⁩
3Main deliverable — final stage⁦2026-09-07⁩
4Final report⁦2026-11-30⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2025-04-04⁩
  2. Contract signed⁦2025-07-11⁩
  3. 50% of works complete⁦2026-02-08⁩
  4. Provisional acceptance⁦2026-10-13⁩
  5. Closure⁦2026-11-30⁩

8Budget

Required at this stage
  • Main contract⁦72.0%⁩SYP2.7B
  • Supervision & consulting⁦14.0%⁩SYP517.5M
  • Internal team⁦9.0%⁩SYP332.5M
  • Contingency reserve (⁦5%⁩)⁦5.0%⁩SYP185M
The delivering body’s investment-plan allocationsTotalSYP3.7B

9Timeline

Required at this stage
Start
2025-04-066 April 2025
Baseline finish
2026-11-3030 November 2026
Duration
⁦20⁩ months

10Key risks

Required at this stage
  • HighExchange-rate swings on imported equipment with unfixed prices
  • MediumLate delivery of cooling units and standby generators

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the unified contracts law (⁦Law 51 of 2004⁩)

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • National Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3⁦Target benefits within 12 months⁩

15Governance structure

Required at this stage
  • Change CommitteeApproves scope, cost and schedule changesWeekly
  • Project Approval CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Authority