Government Backup Data Centre, Homs — Phase 2
Add to watchlistA Tier III standby site in Homs, away from the capital, that keeps the government e-services platform and the ministries’ systems running after a major outage at the main Damascus data centre.
Budget (BAC)
Actual cost
79% of budget
Progress
Estimate at completion
+SYP 365.9M
SPI · CPI
Forecast finish
38 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure13 October 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate5 February 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate6 April 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate11 July 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate13 October 2026Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-08-19 | 2025-10-18 | +60 days | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-12-01 | 2026-03-17 | +106 days | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-05-06 | 2026-10-26 | +173 days | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-08-18 | 2026-12-08 | +112 days | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | Late | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2026-11-30 | 2027-01-09 | +40 days | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
72%Awaiting acceptance
8%Not handed in
20%Deliverable flow
Display options
| Project plan & baseline003-D1 | 5% | CRT-003-01 | Approved | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | Eng. Mazen Kassab | 2025-06-28 | V1 | 3 of 3 |
| Monitoring & reporting003-D2 | 4% | CRT-003-02 | Approved | Eng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.sy | Eng. Mazen Kassab | 2025-08-19 | V1 | 3 of 3 |
| Business requirements003-D3 | 9% | CRT-003-03 | Approved | Eng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.sy | Eng. Mazen Kassab | 2025-10-10 | V1 | 3 of 3 |
| Solution design003-D4 | 9% | CRT-003-04 | Approved | Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy | Eng. Mazen Kassab | 2025-12-01 | V1 | 3 of 3 |
| Release 1003-D5 | 15% | CRT-003-05 | Approved | Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy | Eng. Mazen Kassab | 2026-01-22 | V1 | 3 of 3 |
| Release 2003-D6 | 15% | CRT-003-06 | Approved | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | Eng. Mazen Kassab | 2026-03-15 | V1 | 3 of 3 |
| Integrations003-D7 | 15% | CRT-003-07 | Approved | Eng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.sy | Eng. Mazen Kassab | 2026-05-06 | V1 | 3 of 3 |
| System testing003-D8 | 8% | — | Under review | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy | Eng. Mazen Kassab | 2026-06-27 | V1 | 1 of 3 |
| User acceptance testing003-D9 | 8% | — | Draft | Eng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.sy | Eng. Mazen Kassab | 2026-08-18 | V0 | 0 of 3 |
| Training & change003-D10 | 6% | — | Draft | Eng. Mazen KassabEng. Mazen KassabDirector General, Government Digital InfrastructureP-017mazen.kassab@psa.gov.sy | Eng. Mazen Kassab | 2026-10-09 | V0 | 0 of 3 |
| Go-live & handover003-D11 | 6% | — | Draft | Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationP-011khaled.alkayyali@psa.gov.sy | Eng. Mazen Kassab | 2026-11-30 | V0 | 0 of 3 |
| Total · 11 | 100% |