Original
Original baseline
- Finish
- 2026-11-30
- Budget
- SYP 3.6B
- 16 activities
Approved with the project plan at the planning gate.
Approved 2025-04-06 · by Eng. Khaled Al-Kayyali
A Tier III standby site in Homs, away from the capital, that keeps the government e-services platform and the ministries’ systems running after a major outage at the main Damascus data centre.
Budget (BAC)
Actual cost
79% of budget
Progress
Estimate at completion
+SYP 365.9M
SPI · CPI
Forecast finish
38 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure13 October 2026
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2025-04-06 · by Eng. Khaled Al-Kayyali
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. George Haddad
What changed from version A to version B
Finish
2026-11-302027-01-09
+40 days
Budget
SYP 3.6BSYP 3.7B
+77.50 SYP M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SYP millions from A to B
Every saved version with its reason and reference