CR-2026-002Darayya Replacement Housing

Add a basement parking level to block 3

ScopeApprovedImpact level: Major

Justification and the cost, schedule and risk impact, with a recommendation.

Electronic form

Impact analysis

Before and after — as it will show in the baseline if approved

Cost

+SYP 962.5M

Current budgetSYP 28.5B

After the changeSYP 29.5B

+3.4%

Schedule

+⁦60⁩ d
  • Baseline finish2027-05-01
  • New finish2027-06-30

Risk

+3
9Medium12Medium
Risk RSK-0017 · Contractor claim for a 120-day extension with compensation

Raises the chance of extension claims

Benefits

+9%

420 more parking spaces for residents and visitors

⁦+9⁩% of expected benefits

Reason for change

An updated traffic study expects a parking shortfall for residents and visitors once the blocks and the shops in block 3 are occupied

Justification

Building it now costs about 60% less than a car park later, and eases congestion in the neighbourhood streets

PMO recommendation

Approve with conditions

The PMO recommends approval with a fixed unit rate for the concrete works

Conditions

  • Fix the unit rate for concrete works

Approval workflow

  1. Submitted

    Eng. Qasem Al-Hariri

    Done2026-03-02

  2. PM review

    Eng. Qasem Al-Hariri

    Done2026-03-03

  3. Impact analysis

    Kinan Azzam

    Done2026-03-07

  4. Finance & procurement

    Rasha Al-Mudarres

    Done2026-03-08

  5. Project owner’s acceptance

    Eng. Wassim Al-Azm

    Done2026-03-08

  6. Change committee recommendation

    Dr. Ziad Al-Atassi

    Done2026-03-19

  7. Executive Council decision

    Dr. Samer Al-Daqqar

    Done2026-03-22

  8. Baseline updated

    Eng. Qasem Al-Hariri

    Done2026-03-26

Why this route

The route is built from the request’s kind and impact level under the approved authority matrix.

Impact levelMajorAbove SYP 125M or 90 days

  • A cost impact of SYP 962.5M is above SYP 125M — «major»: the Change Committee recommends and the Executive Council decides.
  • It has a financial link, so Finance & Procurement take part before the decision.
  • It changes scope or deliverables, so the project owner must accept it.

Change committee vote

Members vote before or during the meeting; the decision is taken once quorum is met

  • Dr. Ziad Al-AtassiDeputy President, Strategy & PerformanceDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.syChairApprove
  • Dr. Reem Al-QabbaniDirector, National Project Management OfficeDr. Reem Al-QabbaniDirector, National Project Management OfficeP-002reem.alqabbani@psa.gov.syYouApprove
  • Omar Al-NahhasSenior Finance & Contracts SpecialistOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.syApprove
  • Rasha Al-MudarresDirector General, Finance & ContractsRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.syApprove
  • Eng. Rita GhanemEnterprise ArchitectEng. Rita GhanemEnterprise ArchitectP-031rita.ghanem@psa.gov.syApprove
  • Eng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syApprove
6/6Quorum met
  • Approve6
  • Approve with conditions0
  • Reject0
  • Abstain0

Decided by the committee on 22 March 2026The decision in the log · DEC-2026-009

Baseline

Baseline updated on 26 March 2026