Execution
Change request
The change, its impact analysis and the approval decision
- Form no.
- PSA-PMO-F09
- Template edition
- 3.1
- Version
- V2
- Form date
- 2026-03-02
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-002
- Project
- Darayya Replacement Housing
- Portfolio
- Reconstruction & Infrastructure Portfolio
- Sector
- Development Projects Follow-up Sector
- Sponsor
- Salma Al-Zaim
- Project manager
- Eng. Qasem Al-Hariri
1The change
- TitleAuto-filled
- Add a basement parking level to block 3
- KindAuto-filled
- Scope
- Requested byAuto-filled
- Eng. Qasem Al-Hariri
- Raised onAuto-filled
- 2026-03-02
Reason
An updated traffic study expects a parking shortfall for residents and visitors once the blocks and the shops in block 3 are occupied
Justification
Building it now costs about 60% less than a car park later, and eases congestion in the neighbourhood streets
2Impact analysis
Cost
+SYP 962.5M
Schedule
+60 days
Risk
9 → 12
Benefits
+9%
Risk impact
Raises the chance of extension claims
Benefits impact
420 more parking spaces for residents and visitors
3The approval decision
The PMO’s recommendation
The PMO recommends approval with a fixed unit rate for the concrete works
- Change Committee decision
- Approve with conditions
- Decided on
- 2026-03-22
- Decision number
- DEC-2026-009
Conditions
- Fix the unit rate for concrete works
Approval logChain: Change request approval · version 5
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Qasem Al-HaririDirector, Transport & Housing Projects | Submitted | — | 2026-03-02 11:26 |
| 2 | Project manager | Technical acceptance | Eng. Qasem Al-HaririProject manager | Approved | — | 2026-03-03 13:10 |
| 3 | PMO review & impact analysis | Methodology review | Mariam Al-ZoubiPMO — analyst | Approved | — | 2026-03-05 14:17 |
| 4 | Financial impact | Financial approval | Rasha Al-MudarresFinance | Approved | — | 2026-03-09 12:45 |
| 5 | Contractual impact | Financial approval | Abdullah Al-UjailiProcurement & contracts | Approved | — | 2026-03-10 13:22 |
| 6 | Change Committee | Technical acceptance | Dr. Ziad Al-AtassiChange Committee | Approved | — | 2026-03-15 11:38 |
| 7 | National Projects Steering Committee | Technical acceptance | Approval engineNational Projects Steering Committee | Pre-breach alert | — | 2026-03-23 08:00 |
| 8 | National Projects Steering Committee | Technical acceptance | Dr. Samer Al-DaqqarNational Projects Steering Committee | Approved | — | 2026-03-24 14:53 |
Signatures
Project manager
Eng. Qasem Al-Hariri
Approved2026-03-03
PMO review & impact analysis
Mariam Al-Zoubi
Approved2026-03-05
Financial impact
Rasha Al-Mudarres
Approved2026-03-09
Contractual impact
Abdullah Al-Ujaili
Approved2026-03-10
Change Committee
Dr. Ziad Al-Atassi
Approved2026-03-15
National Projects Steering Committee
Dr. Samer Al-Daqqar
Approved2026-03-24