Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-002Off track4ExecutionConstructionStalledDelivered by:Ministry of Public Works and Housing

Darayya Replacement Housing

Remove from watchlist

Replacement housing for families returning to Darayya — four linked residential blocks with water, power and internal roads, a school and a health centre, on land allocated by Rif Dimashq Governorate.

Early warning: ⁦88%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SYP 29.5B

Actual cost

SYP 13.3B

⁦45%⁩ of budget

Progress

⁦42%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 31.7B

+SYP 2.2B

SPI · CPI

0.82Schedule performance index · 0.820.93Cost performance index · 0.93

Forecast finish

⁦2027-09-12⁩

74 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure25 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 January 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 March 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate13 September 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate25 March 2027Closure · Not startedClosure · Not started

Change request

The change, its impact analysis and the approval decision

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Change request

The change, its impact analysis and the approval decision

Form no.
PSA-PMO-F09
Template edition
3.1
Version
V2
Form date
⁦2026-03-02⁩
ApprovedCR-2026-002Add a basement parking level to block 3

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-002
Project
Darayya Replacement Housing
Portfolio
Reconstruction & Infrastructure Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Qasem Al-Hariri

1The change

TitleAuto-filled
Add a basement parking level to block 3
KindAuto-filled
Scope
Requested byAuto-filled
Eng. Qasem Al-Hariri
Raised onAuto-filled
⁦2026-03-02⁩

Reason

An updated traffic study expects a parking shortfall for residents and visitors once the blocks and the shops in block 3 are occupied

Justification

Building it now costs about 60% less than a car park later, and eases congestion in the neighbourhood streets

2Impact analysis

Cost

+SYP 962.5M

Schedule

+60 days

Risk

9 → 12

Benefits

+9%

Risk impact

Raises the chance of extension claims

Benefits impact

420 more parking spaces for residents and visitors

3The approval decision

The PMO’s recommendation

The PMO recommends approval with a fixed unit rate for the concrete works

Change Committee decision
Approve with conditions
Decided on
⁦2026-03-22⁩
Decision number
DEC-2026-009

Conditions

  • Fix the unit rate for concrete works

Approval logChain: Change request approval · version ⁦5⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Qasem Al-HaririDirector, Transport & Housing ProjectsSubmitted—⁦2026-03-02⁩ 11:26
2Project managerTechnical acceptanceEng. Qasem Al-HaririProject managerApproved—⁦2026-03-03⁩ 13:10
3PMO review & impact analysisMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2026-03-05⁩ 14:17
4Financial impactFinancial approvalRasha Al-MudarresFinanceApproved—⁦2026-03-09⁩ 12:45
5Contractual impactFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2026-03-10⁩ 13:22
6Change CommitteeTechnical acceptanceDr. Ziad Al-AtassiChange CommitteeApproved—⁦2026-03-15⁩ 11:38
7National Projects Steering CommitteeTechnical acceptanceApproval engineNational Projects Steering CommitteePre-breach alert—⁦2026-03-23⁩ 08:00
8National Projects Steering CommitteeTechnical acceptanceDr. Samer Al-DaqqarNational Projects Steering CommitteeApproved—⁦2026-03-24⁩ 14:53

Signatures

Project manager

Eng. Qasem Al-Hariri

Approved⁦2026-03-03⁩

PMO review & impact analysis

Mariam Al-Zoubi

Approved⁦2026-03-05⁩

Financial impact

Rasha Al-Mudarres

Approved⁦2026-03-09⁩

Contractual impact

Abdullah Al-Ujaili

Approved⁦2026-03-10⁩

Change Committee

Dr. Ziad Al-Atassi

Approved⁦2026-03-15⁩

National Projects Steering Committee

Dr. Samer Al-Daqqar

Approved⁦2026-03-24⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F09 · version V2

Change request

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Change request approval · version ⁦5⁩

Submitted by Eng. Qasem Al-Hariri on ⁦2026-03-02⁩

  1. Technical acceptance

    Project manager

    Eng. Qasem Al-Hariri · Project manager

    Approved · ⁦2026-03-03⁩ at ⁦13:10⁩

  2. Methodology review

    PMO review & impact analysis

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2026-03-05⁩ at ⁦14:17⁩

  3. Financial approval

    Financial impact

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2026-03-09⁩ at ⁦12:45⁩

  4. Financial approval

    Contractual impact

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2026-03-10⁩ at ⁦13:22⁩

  5. Technical acceptance

    Change Committee

    Dr. Ziad Al-Atassi · Change Committee

    Approved · ⁦2026-03-15⁩ at ⁦11:38⁩

  6. Technical acceptance

    National Projects Steering Committee

    Dr. Samer Al-Daqqar · National Projects Steering Committee

    On the path because: Cost impact above the Change Committee’s authority?From the authority matrix

    Approved · ⁦2026-03-24⁩ at ⁦14:53⁩

Steps that do not apply to this record

  • Authority Executive Council — the condition «Cost impact above the Steering Committee’s authority?» does not holdFrom the authority matrix

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2026-03-22⁩

    Approved by the committee

    • Fix the unit rate for concrete works

    Eng. Qasem Al-Hariri

  2. V1Returned for edit⁦2026-03-02⁩

    The request as raised

    Eng. Qasem Al-Hariri

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close