PRJ-2026-002Off track4ExecutionConstructionStalledDelivered by:Ministry of Public Works and Housing
Darayya Replacement Housing
Remove from watchlistReplacement housing for families returning to Darayya — four linked residential blocks with water, power and internal roads, a school and a health centre, on land allocated by Rif Dimashq Governorate.
Project managerEng. Qasem Al-HaririProject sponsorSalma Al-ZaimProgrammeDamaged Areas Reconstruction Programme
Early warning: 88% chance of slipping within 60 days
Budget (BAC)
SYP 29.5B
Actual cost
SYP 13.3B
45% of budget
Progress
42%Awaiting acceptance 11%
Estimate at completion
SYP 31.7B
+SYP 2.2B
SPI · CPI
0.82Schedule performance index · 0.820.93Cost performance index · 0.93
Forecast finish
2027-09-12
74 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure25 March 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 January 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate3 March 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate13 September 2024Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate25 March 2027Closure · Not startedClosure · Not started