Darayya Replacement Housing
Remove from watchlistReplacement housing for families returning to Darayya — four linked residential blocks with water, power and internal roads, a school and a health centre, on land allocated by Rif Dimashq Governorate.
Budget (BAC)
Actual cost
45% of budget
Progress
Estimate at completion
+SYP 2.2B
SPI · CPI
Forecast finish
74 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure25 March 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 January 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate3 March 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate13 September 2024Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate25 March 2027Closure · Not startedClosure · Not started
Team & roles
4 members, about 1.4 full-time equivalents
Leadership
2 members
- Eng. Qasem Al-HaririProject manager60%Allocated 125% across all projectsA
- Eng. Abdulrahman Al-KilaniFollow-up lead — handing units over to returning families20%Allocated 110% across all projectsR
Specialists
1 member
- Huda Al-DandalFinancial analyst15%C
Vendor team & advisers
1 member
A AccountableR ResponsibleC ConsultedI Informed
Stakeholders
6 stakeholders, 4 of them below the engagement needed
Power / interest matrix
Pick one to see how they are handled
Keep satisfied1
high power, lower interest
Manage closely4
high power and interest
Monitor0
minimal effort
Keep informed1
high interest, lower power
Interest
Project sponsor
Salma Al-Zaim
Decisions and funding
Influence
Interest
Engagement level
Unaware
Resistant
Neutral
Supportive
Leading
A gap of 1 step — needs an engagement plan.
- Impact on the project
- Approves gates and changes
- Engagement plan
- Monthly briefing
Display options
| Organisation | Role | Actions | ||||||
|---|---|---|---|---|---|---|---|---|
| Salma Al-Zaim | Project sponsor | Decisions and funding | SupportiveLeading | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy | 2026-10-20 | |||
| Eng. Wassim Al-Azm | Project owner | Accepts deliverables, owns benefits | ResistantLeading | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy | 2026-10-23 | |||
| Project Management Office (PMO) | Governance | Compliance and data quality | Supportive | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy | 2026-10-17 | |||
| General Directorate of Financial Affairs | Internal department | Payment approval | NeutralSupportive | Huda Al-DandalHuda Al-DandalSenior Financial Analyst — Investment PlanP-037huda.aldandal@psa.gov.sy | 2026-10-14 | |||
| Al-Bunyan Al-Mateen Contracting Co. | Main vendor | Delivers the contracted work | Supportive | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy | 2026-10-24 | |||
| End beneficiaries | Beneficiaries | Users of the outcome | NeutralSupportive | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy | 2026-09-26 |
Communication plan
Who needs what, when, through which channel, and who owns it.
- Project sponsorStatus and decisions neededMonthlyMeetingEng. Qasem Al-Hariri2026-11-15
- Project ownerDeliverable status and acceptance datesFortnightlyEmailEng. Qasem Al-Hariri2026-11-03Overdue
- PMOData and indicator updatesWeeklyDashboardEng. Qasem Al-Hariri2026-10-31
- BeneficiariesWhat changes and whenAt milestonesNewsletterEng. Qasem Al-HaririAt launch
Coming up
By date
- 312026-10PMODashboard · Weekly
- 032026-11Project ownerEmail · Fortnightly
- 152026-11Project sponsorMeeting · Monthly