PRJ-2026-002Off track4ExecutionConstructionStalledDelivered by:Ministry of Public Works and Housing

Darayya Replacement Housing

Remove from watchlist

Replacement housing for families returning to Darayya — four linked residential blocks with water, power and internal roads, a school and a health centre, on land allocated by Rif Dimashq Governorate.

Early warning: ⁦88%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SYP 29.5B

Actual cost

SYP 13.3B

⁦45%⁩ of budget

Progress

⁦42%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 31.7B

+SYP 2.2B

SPI · CPI

0.82Schedule performance index · 0.820.93Cost performance index · 0.93

Forecast finish

⁦2027-09-12⁩

74 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure25 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 January 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 March 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate13 September 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate25 March 2027Closure · Not startedClosure · Not started

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
PSA-PMO-F05
Template edition
2.0
Version
V2
Form date
⁦2024-03-28⁩
ApprovedPRJ-2026-002Darayya Replacement Housing

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-002
Project
Darayya Replacement Housing
Portfolio
Reconstruction & Infrastructure Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Qasem Al-Hariri

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2024-03-03⁩

Baseline finish

⁦2027-06-30⁩

Forecast finish

⁦2027-09-12⁩

SPI

0.82

MilestonePlannedForecastSlip
Project plan approved⁦2024-11-09⁩⁦2025-05-27⁩+199 days
Designs approved⁦2025-05-20⁩⁦2026-05-07⁩+352 days
Build complete⁦2026-03-05⁩⁦2027-01-17⁩+318 days
Testing & acceptance complete⁦2026-12-19⁩⁦2027-06-19⁩+182 days
Final handover⁦2027-06-30⁩⁦2027-09-29⁩+91 days

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦4%⁩⁦2024-08-04⁩Eng. Qasem Al-Hariri
Monitoring & reporting⁦4%⁩⁦2024-11-09⁩Eng. Wassim Al-Azm
Detailed design⁦8%⁩⁦2025-02-13⁩Eng. Wassim Al-Azm
Permits & approvals⁦8%⁩⁦2025-05-20⁩Salma Al-Zaim
Site works & excavation⁦18%⁩⁦2025-08-25⁩Salma Al-Zaim
Structure⁦11%⁩⁦2025-11-29⁩Eng. Qasem Al-Hariri
Finishes⁦11%⁩⁦2026-03-05⁩Eng. Wassim Al-Azm
Supply⁦8%⁩⁦2026-06-10⁩Eng. Qasem Al-Hariri
Installation⁦8%⁩⁦2026-09-14⁩Eng. Wassim Al-Azm
Testing & commissioning⁦8%⁩⁦2026-12-19⁩Salma Al-Zaim
Provisional acceptance⁦6%⁩⁦2027-03-26⁩Eng. Wassim Al-Azm
Final acceptance⁦6%⁩⁦2027-06-30⁩Salma Al-Zaim
Accepted with a certificate⁦42%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
RSK-0015Steel and concrete price rises driving price-adjustment claims20EscalateEng. Qasem Al-Hariri
RSK-0016Late hand-over of the northern plot and utility diversions in blocks 3 and 420EscalateEng. Wassim Al-Azm
RSK-0017Contractor claim for a 120-day extension with compensation16MitigateOmar Al-Nahhas
RSK-0018Safety incidents around cranes and deep excavations10MitigateEng. Qasem Al-Hariri

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyEng. Qasem Al-Hariri
Project ownerDeliverable status and acceptance datesFortnightlyEng. Qasem Al-Hariri
PMOData and indicator updatesWeeklyEng. Qasem Al-Hariri
BeneficiariesWhat changes and whenAt each milestoneEng. Qasem Al-Hariri
Team memberRoleAllocation
Eng. Qasem Al-HaririProject manager⁦60%⁩
Eng. Abdulrahman Al-KilaniFollow-up lead — handing units over to returning families⁦20%⁩
Huda Al-DandalFinancial analyst⁦15%⁩
—Planning & scheduling engineer⁦50%⁩

5QualityAuto-filled

Quality leadAuto-filled
Eng. Wael Al-Khawlani
Review cadenceAuto-filled
Inspection before every pour across the six buildings; backfill tests in every zone
Next reviewAuto-filled
⁦2026-11-05⁩
Quality criterionThresholdNowMet
Backfill compaction under the slabs95% of max dry density or more92.8% in zone 3No
Floor screed thickness50 mm ±551 mm after repairYes
Fire rating of doors and separating walls120 minutes or more120 minutes in the tested samplesYes

6BenefitsAuto-filled

BenefitBaselineTargetOwner
No benefits recorded

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Qasem Al-HaririDirector, Transport & Housing ProjectsSubmitted—⁦2024-03-28⁩ 12:03
2Methodology review — PMOMethodology reviewMariam Al-ZoubiPMO — analystApprovedComplete against the project management plan template.⁦2024-04-02⁩ 14:05
3Technical acceptance — project ownerTechnical acceptanceEng. Wassim Al-AzmProject ownerApproved—⁦2024-04-03⁩ 09:12
4Cash flow & financial commitmentFinancial approvalRasha Al-MudarresFinanceApproved—⁦2024-04-04⁩ 13:58
5Plan aligned with the contractsFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2024-04-08⁩ 14:35
6Sponsor approvalTechnical acceptanceSalma Al-ZaimProject sponsorApproved—⁦2024-04-09⁩ 12:33

Signatures

Methodology review — PMO

Mariam Al-Zoubi

Approved⁦2024-04-02⁩

Technical acceptance — project owner

Eng. Wassim Al-Azm

Approved⁦2024-04-03⁩

Cash flow & financial commitment

Rasha Al-Mudarres

Approved⁦2024-04-04⁩

Plan aligned with the contracts

Abdullah Al-Ujaili

Approved⁦2024-04-08⁩

Sponsor approval

Salma Al-Zaim

Approved⁦2024-04-09⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F05 · version V2

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Eng. Qasem Al-Hariri on ⁦2024-03-28⁩

  1. Methodology review

    Methodology review — PMO

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2024-04-02⁩ at ⁦14:05⁩

    Complete against the project management plan template.

  2. Technical acceptance

    Technical acceptance — project owner

    Eng. Wassim Al-Azm · Project owner

    Approved · ⁦2024-04-03⁩ at ⁦09:12⁩

  3. Financial approval

    Cash flow & financial commitment

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2024-04-04⁩ at ⁦13:58⁩

  4. Financial approval

    Plan aligned with the contracts

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2024-04-08⁩ at ⁦14:35⁩

  5. Technical acceptance

    Sponsor approval

    Salma Al-Zaim · Project sponsor

    Approved · ⁦2024-04-09⁩ at ⁦12:33⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-03-28⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Eng. Qasem Al-Hariri

  2. V1Returned for edit⁦2024-03-14⁩

    First draft — returned to complete the quality plan

    • Plan from the methodology template

    Eng. Qasem Al-Hariri