Original
Original baseline
- Finish
- 2027-06-30
- Budget
- SYP 28.5B
- 17 activities
Approved with the project plan at the planning gate.
Approved 2024-03-03 · by Salma Al-Zaim
Replacement housing for families returning to Darayya — four linked residential blocks with water, power and internal roads, a school and a health centre, on land allocated by Rif Dimashq Governorate.
Budget (BAC)
Actual cost
45% of budget
Progress
Estimate at completion
+SYP 2.2B
SPI · CPI
Forecast finish
74 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure25 March 2027
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2024-03-03 · by Salma Al-Zaim
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. Qasem Al-Hariri
What changed from version A to version B
Finish
2027-06-302027-09-29
+91 days
Budget
SYP 28.5BSYP 29.5B
+962.50 SYP M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SYP millions from A to B
Every saved version with its reason and reference