PRJ-2026-002Off track4ExecutionConstructionStalledDelivered by:Ministry of Public Works and Housing

Darayya Replacement Housing

Remove from watchlist

Replacement housing for families returning to Darayya — four linked residential blocks with water, power and internal roads, a school and a health centre, on land allocated by Rif Dimashq Governorate.

Early warning: ⁦88%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SYP 29.5B

Actual cost

SYP 13.3B

⁦45%⁩ of budget

Progress

⁦42%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 31.7B

+SYP 2.2B

SPI · CPI

0.82Schedule performance index · 0.820.93Cost performance index · 0.93

Forecast finish

⁦2027-09-12⁩

74 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure25 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 January 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 March 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate13 September 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate25 March 2027Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−21

May to October 2026

No material change in the health dimensions over the period.

AI insight

⁦88%⁩ chance of a further slip within ⁦60⁩ days

From the SPI trend (⁦0.82⁩), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.

Confidence⁦82%⁩

Copilot summary

Generated from the live project data

The project is behind plan: ⁦42% done against 51% planned⁩.

⁦SPI 0⁩.⁦82⁩, ⁦CPI 0⁩.⁦93⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Reconstruction & InfrastructureSO-2.2Rebuild damaged areas and provide replacement housing

Main initiative

SI-2.2.1Replacement housing & rebuilding damaged areas

Contribution to the initiative⁦58%⁩

The project’s share of the initiative’s project budget (3 projects)

Secondary links

Annual work-plan line
WP-2024-002
Classification
Strategic

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦42%⁩

Awaiting acceptance ⁦11%⁩

Not handed in ⁦47%⁩

5 deliverables accepted

  • Site works & excavation⁦18%⁩
  • Detailed design⁦8%⁩
  • Permits & approvals⁦8%⁩
  • Project plan & baseline⁦4%⁩
  • Monitoring & reporting⁦4%⁩

1 deliverable under inspection or acceptance

  • Structure⁦11%⁩

Corrective plan requiredThe project is seriously late (74 days late · SPI ⁦0.82⁩) and has no corrective plan yet.

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦93%⁩ of budget

SYP13.3B/ SYP29.5BSYP2.2Bprojected overrun(⁦7.5%⁩)
Actual spend
SYP13.3B
Committed
SYP27.4B
Approved budget
SYP29.5B
Estimate at completion
SYP31.7B

Next milestones

  • Provisional acceptance⁦2027-05-20⁩was ⁦2027-03-25⁩Late
  • Closure⁦2027-09-12⁩was ⁦2027-06-30⁩Late

Waiting on someone

⁦1⁩ approval and ⁦2⁩ open actions on this project

Approvals & requests

From «My actions» for this project

Actions

⁦2⁩ open

  • Ask the electricity transmission & distribution establishment to move the HV lineEng. Wassim Al-Azm3 days overdue2026-10-25High
  • Analyse the budget impact of price adjustmentsHuda Al-DandalIn 13 days2026-11-10High

Risks & impediments

4 open risks, exposure SYP 2.5B

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩1Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩RSK-0015Steel and concrete price rises driving price-adjustment claimsProbability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩1Probability: Likely · Impact: MajorHigh · Score ⁦16⁩RSK-0017Contractor claim for a 120-day extension with compensation1Probability: Likely · Impact: SevereCritical · Score ⁦20⁩RSK-0016Late hand-over of the northern plot and utility diversions in blocks 3 and 4
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩1Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩RSK-0018Safety incidents around cranes and deep excavations
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical2
  • High1
  • Medium1
  • Low0

Deliverables

⁦5⁩ of ⁦12⁩ approved

  • Project plan & baseline002-D1 · V1 · CRT-002-01⁦4%⁩Eng. Qasem Al-Hariri2024-08-042024-08-04Approved
  • Monitoring & reporting002-D2 · V1 · CRT-002-02⁦4%⁩Eng. Wassim Al-Azm2024-11-092024-11-09Approved
  • Detailed design002-D3 · V1 · CRT-002-03⁦8%⁩Eng. Wassim Al-Azm2025-02-132025-02-13Approved
  • Permits & approvals002-D4 · V1 · CRT-002-04⁦8%⁩Salma Al-Zaim2025-05-202025-05-20Approved
  • Site works & excavation002-D5 · V1 · CRT-002-05⁦18%⁩Salma Al-Zaim2025-08-252025-08-25Approved
  • Structure002-D6 · V1⁦11%⁩Eng. Qasem Al-Hariri333 days overdue2025-11-29In review
  • Finishes002-D7 · V0⁦11%⁩Eng. Wassim Al-Azm237 days overdue2026-03-05Draft
  • Supply002-D8 · V0⁦8%⁩Eng. Qasem Al-Hariri140 days overdue2026-06-10Draft
  • Installation002-D9 · V0⁦8%⁩Eng. Wassim Al-Azm44 days overdue2026-09-14Draft
  • Testing & commissioning002-D10 · V0⁦8%⁩Salma Al-ZaimIn 52 days2026-12-19Draft
  • Provisional acceptance002-D11 · V0⁦6%⁩Eng. Wassim Al-AzmIn 149 days2027-03-26Draft
  • Final acceptance002-D12 · V0⁦6%⁩Salma Al-ZaimIn 245 days2027-06-30Draft

Team, contracts & documents

Team

4 members

Eng. Qasem Al-Hariri · Director, Transport & Housing ProjectsEng. Abdulrahman Al-Kilani · Deputy President, Development Projects Follow-upHuda Al-Dandal · Senior Financial Analyst — Investment Plan
  • Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsProject managerP-020qasem.alhariri@psa.gov.sy⁦60%⁩
  • Eng. Abdulrahman Al-KilaniEng. Abdulrahman Al-KilaniDeputy President, Development Projects Follow-upFollow-up lead — handing units over to returning familiesP-010abdulrahman.alkilani@psa.gov.sy⁦20%⁩
  • Huda Al-DandalHuda Al-DandalSenior Financial Analyst — Investment PlanFinancial analystP-037huda.aldandal@psa.gov.sy⁦15%⁩
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close