Certificate ⁦28⁩ — September 2026

Darayya replacement housing — construction

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
28
Date
⁦2026-10-07⁩
Reference
PAY-2026-015

Interim payment certificate no. (⁦28⁩)

For the work of September 2026

Contract number
PSA/2024/011
Tender file no.
2401780147
Contract
Darayya replacement housing — construction
Contractor
Al-Bunyan Al-Mateen Contracting Co.
Contractor tax number
TX-403137
Project
Darayya Replacement Housing
Contract period
⁦2024-04-01⁩ — ⁦2027-06-30⁩
Original contract value
SYP25,500,000,000
Current contract value
SYP26,462,500,000including variations of SYP 962.5M
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SYP)

1Total value of work completed to date11,325,000,000
2Less: previous certificates(10,955,000,000)
3Value of work in this certificate370,000,000
4Less: retention (⁦10%⁩)(37,000,000)
5Less: advance payment recovery (⁦10%⁩)(37,000,000)
6Less: delay and breach penalties0
7Total deductions(74,000,000)
8Net amount payable to the contractorSYP296,000,000

Amount in words: Two hundred ninety-six million Syrian pounds only

Retention held up to this certificate: SYP 1.1B — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation1,852,375,0001,777,900,00051,075,0001,828,975,000⁦99%⁩
Earthworks & foundations4,763,250,0002,770,625,00083,275,0002,853,900,000⁦60%⁩
Concrete & structural works8,203,375,0003,734,675,000127,150,0003,861,825,000⁦47%⁩
Mechanical, electrical & plumbing6,351,000,0001,830,475,00072,125,0001,902,600,000⁦30%⁩
Finishes & external works3,969,375,000733,075,00031,375,000764,450,000⁦19%⁩
Testing & commissioning1,323,125,000108,250,0005,000,000113,250,000⁦9%⁩
Total26,462,500,00010,955,000,000370,000,00011,325,000,000⁦43%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Anas Al-Sheikh

Al-Sheikh⁦2026-10-07⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-10-12⁩

Project manager

Eng. Qasem Al-Hariri

Al-Hariri⁦2026-10-19⁩

Finance & contracts

Omar Al-Nahhas

Awaiting signature

Final approver

Dr. Samer Al-Daqqar

Later
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Current step: Payment order prepared

  1. Certificate submitted⁦2026-10-07⁩

    Eng. Anas Al-Sheikh

  2. Engineer verifies quantities⁦2026-10-12⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 5 days

  3. Project manager certifies⁦2026-10-19⁩

    Eng. Qasem Al-Hariri · Director, Transport & Housing Projects

    Took 7 days

  4. Payment order preparedDue today2026-10-28

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Waiting for Omar Al-Nahhas
  5. Final approval

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeLate · ⁦2026-01-13⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Qasem Al-Hariri → Dr. Samer Al-Daqqar

Certificate history

19 October 2026

  1. Approval: Eng. Qasem Al-Hariri signed “Project manager certifies”

    2026-10-19 13:00

12 October 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-10-12 13:00

7 October 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-10-07 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close