Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 25
- Date
- 2026-07-05
- Reference
- PAY-2024-011-25
Interim payment certificate no. (25)
For the work of June 2026
- Contract number
- PSA/2024/011
- Tender file no.
- 2401780147
- Contract
- Darayya replacement housing — construction
- Contractor
- Al-Bunyan Al-Mateen Contracting Co.
- Contractor tax number
- TX-403137
- Project
- Darayya Replacement Housing
- Contract period
- 2024-04-01 — 2027-06-30
- Original contract value
- SYP25,500,000,000
- Current contract value
- SYP26,462,500,000including variations of SYP 962.5M
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 10,361,250,000 |
| 2 | Less: previous certificates | (10,154,500,000) |
| 3 | Value of work in this certificate | 206,750,000 |
| 4 | Less: retention (10%) | (20,675,000) |
| 5 | Less: advance payment recovery (10%) | (20,675,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (41,350,000) |
| 8 | Net amount payable to the contractor | SYP165,400,000 |
Amount in words: One hundred sixty-five million four hundred thousand Syrian pounds only
Retention held up to this certificate: SYP 1B — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 1,852,375,000 | 1,644,225,000 | 29,125,000 | 1,673,350,000 | 90% |
| Earthworks & foundations | 4,763,250,000 | 2,563,850,000 | 47,175,000 | 2,611,025,000 | 55% |
| Concrete & structural works | 8,203,375,000 | 3,462,200,000 | 70,975,000 | 3,533,175,000 | 43% |
| Mechanical, electrical & plumbing | 6,351,000,000 | 1,701,050,000 | 39,650,000 | 1,740,700,000 | 27% |
| Finishes & external works | 3,969,375,000 | 682,275,000 | 17,100,000 | 699,375,000 | 18% |
| Testing & commissioning | 1,323,125,000 | 100,900,000 | 2,725,000 | 103,625,000 | 8% |
| Total | 26,462,500,000 | 10,154,500,000 | 206,750,000 | 10,361,250,000 | 39% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Anas Al-Sheikh
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. Qasem Al-Hariri
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar