PSA/2024/011
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
Variations pending: 1 worth SYP 105M — if approved the value becomes SYP 26.6B
41% of the current value paid
Paid
SYP11Bof a current value of SYP 26.5B
Value of each certificate
The last 14 — gross and net
Approved: 27
Count: 28 · in the approval chain: 1
| Certificate | Submitted | Gross | Retention | Deductions | Net | Status | |
|---|---|---|---|---|---|---|---|
| Certificate 28September 2026 | 2026-10-07 | SYP370M | SYP37M | SYP37M | SYP296M | In review | |
| Certificate 27August 2026 | 2026-09-07 | SYP422.5M | SYP42.3M | SYP42.3M | SYP338M | Approved | |
| Certificate 26July 2026 | 2026-08-06 | SYP171.3M | SYP17.1M | SYP17.1M | SYP137M | Approved | |
| Certificate 25June 2026 | 2026-07-05 | SYP206.8M | SYP20.7M | SYP20.7M | SYP165.4M | Approved | |
| Certificate 24May 2026 | 2026-06-02 | SYP274.8M | SYP27.5M | SYP27.5M | SYP219.8M | Approved | |
| Certificate 23April 2026 | 2026-05-01 | SYP320.5M | SYP32.1M | SYP32.1M | SYP256.4M | Approved | |
| Certificate 22March 2026 | 2026-03-29 | SYP326.5M | SYP32.7M | SYP32.7M | SYP261.2M | Approved | |
| Certificate 21February 2026 | 2026-02-25 | SYP431M | SYP43.1M | SYP43.1M | SYP344.8M | Approved | |
| Certificate 20January 2026 | 2026-01-23 | SYP421.8M | SYP42.2M | SYP42.2M | SYP337.4M | Approved | |
| Certificate 19December 2025 | 2025-12-22 | SYP441M | SYP44.1M | SYP44.1M | SYP352.8M | Approved | |
| Certificate 18October 2025 | 2025-11-19 | SYP546.8M | SYP54.7M | SYP54.7M | SYP437.4M | Approved | |
| Certificate 17September 2025 | 2025-10-18 | SYP474M | SYP47.4M | SYP47.4M | SYP379.2M | Approved | |
| Certificate 16August 2025 | 2025-09-15 | SYP538.8M | SYP53.9M | SYP53.9M | SYP431M | Approved | |
| Certificate 15July 2025 | 2025-08-14 | SYP590M | SYP59M | SYP59M | SYP472M | Approved | |
| Certificate 14June 2025 | 2025-07-12 | SYP492M | SYP49.2M | SYP49.2M | SYP393.6M | Approved | |
| Certificate 13May 2025 | 2025-06-10 | SYP591.8M | SYP59.2M | SYP59.2M | SYP473.4M | Approved | |
| Certificate 12April 2025 | 2025-05-08 | SYP557.5M | SYP55.8M | SYP55.8M | SYP446M | Approved | |
| Certificate 11March 2025 | 2025-04-06 | SYP485.8M | SYP48.6M | SYP48.6M | SYP388.6M | Approved | |
| Certificate 10February 2025 | 2025-03-04 | SYP572M | SYP57.2M | SYP57.2M | SYP457.6M | Approved | |
| Certificate 9January 2025 | 2025-01-31 | SYP472M | SYP47.2M | SYP47.2M | SYP377.6M | Approved | |
| Certificate 8December 2024 | 2024-12-29 | SYP448.3M | SYP44.8M | SYP44.8M | SYP358.6M | Approved | |
| Certificate 7November 2024 | 2024-11-27 | SYP475M | SYP47.5M | SYP47.5M | SYP380M | Approved | |
| Certificate 6October 2024 | 2024-10-25 | SYP363.5M | SYP36.4M | SYP36.4M | SYP290.8M | Approved | |
| Certificate 5September 2024 | 2024-09-23 | SYP363M | SYP36.3M | SYP36.3M | SYP290.4M | Approved | |
| Certificate 4August 2024 | 2024-08-21 | SYP326.8M | SYP32.7M | SYP32.7M | SYP261.4M | Approved | |
| Certificate 3June 2024 | 2024-07-20 | SYP247.5M | SYP24.8M | SYP24.8M | SYP198M | Approved | |
| Certificate 2May 2024 | 2024-06-17 | SYP226M | SYP22.6M | SYP22.6M | SYP180.8M | Approved | |
| Certificate 1April 2024 | 2024-05-16 | SYP168.5M | SYP16.9M | SYP16.9M | SYP134.8M | Approved |