Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Certificate ⁦19⁩ — December 2025

Darayya replacement housing — construction

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
19
Date
⁦2025-12-22⁩
Reference
PAY-2024-011-19

Interim payment certificate no. (⁦19⁩)

For the work of December 2025

Contract number
PSA/2024/011
Tender file no.
2401780147
Contract
Darayya replacement housing — construction
Contractor
Al-Bunyan Al-Mateen Contracting Co.
Contractor tax number
TX-403137
Project
Darayya Replacement Housing
Contract period
⁦2024-04-01⁩ — ⁦2027-06-30⁩
Original contract value
SYP25,500,000,000
Current contract value
SYP26,462,500,000including variations of SYP 962.5M
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SYP)

1Total value of work completed to date8,380,000,000
2Less: previous certificates(7,939,000,000)
3Value of work in this certificate441,000,000
4Less: retention (⁦10%⁩)(44,100,000)
5Less: advance payment recovery (⁦10%⁩)(44,100,000)
6Less: delay and breach penalties0
7Total deductions(88,200,000)
8Net amount payable to the contractorSYP352,800,000

Amount in words: Three hundred fifty-two million eight hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 838M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation1,852,375,0001,289,025,00064,350,0001,353,375,000⁦73%⁩
Earthworks & foundations4,763,250,0002,008,525,000103,225,0002,111,750,000⁦44%⁩
Concrete & structural works8,203,375,0002,706,425,000151,150,0002,857,575,000⁦35%⁩
Mechanical, electrical & plumbing6,351,000,0001,325,850,00082,000,0001,407,850,000⁦22%⁩
Finishes & external works3,969,375,000530,800,00034,850,000565,650,000⁦14%⁩
Testing & commissioning1,323,125,00078,375,0005,425,00083,800,000⁦6%⁩
Total26,462,500,0007,939,000,000441,000,0008,380,000,000⁦32%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Anas Al-Sheikh

Al-Sheikh⁦2025-12-22⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2025-12-24⁩

Project manager

Eng. Qasem Al-Hariri

Al-Hariri⁦2025-12-27⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2025-12-30⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-01-02⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-12-22⁩

    Eng. Anas Al-Sheikh

  2. Engineer verifies quantities⁦2025-12-24⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2025-12-27⁩

    Eng. Qasem Al-Hariri · Director, Transport & Housing Projects

    Took 3 days

  4. Payment order prepared⁦2025-12-30⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-01-02⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeLate · ⁦2026-01-13⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Qasem Al-Hariri → Dr. Samer Al-Daqqar

Certificate history

2 January 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-01-02 13:00

30 December 2025

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2025-12-30 13:00

27 December 2025

  1. Approval: Eng. Qasem Al-Hariri signed “Project manager certifies”

    2025-12-27 13:00

24 December 2025

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2025-12-24 13:00

22 December 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-12-22 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close