Certificate ⁦18⁩ — October 2025

Darayya replacement housing — construction

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
18
Date
⁦2025-11-19⁩
Reference
PAY-2024-011-18

Interim payment certificate no. (⁦18⁩)

For the work of October 2025

Contract number
PSA/2024/011
Tender file no.
2401780147
Contract
Darayya replacement housing — construction
Contractor
Al-Bunyan Al-Mateen Contracting Co.
Contractor tax number
TX-403137
Project
Darayya Replacement Housing
Contract period
⁦2024-04-01⁩ — ⁦2027-06-30⁩
Original contract value
SYP25,500,000,000
Current contract value
SYP26,462,500,000including variations of SYP 962.5M
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SYP)

1Total value of work completed to date7,939,000,000
2Less: previous certificates(7,392,250,000)
3Value of work in this certificate546,750,000
4Less: retention (⁦10%⁩)(54,675,000)
5Less: advance payment recovery (⁦10%⁩)(54,675,000)
6Less: delay and breach penalties0
7Total deductions(109,350,000)
8Net amount payable to the contractorSYP437,400,000

Amount in words: Four hundred thirty-seven million four hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 793.9M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation1,852,375,0001,201,800,00080,350,0001,282,150,000⁦69%⁩
Earthworks & foundations4,763,250,0001,872,000,000128,625,0002,000,625,000⁦42%⁩
Concrete & structural works8,203,375,0002,519,875,000187,325,0002,707,200,000⁦33%⁩
Mechanical, electrical & plumbing6,351,000,0001,232,725,000101,025,0001,333,750,000⁦21%⁩
Finishes & external works3,969,375,000493,100,00042,775,000535,875,000⁦14%⁩
Testing & commissioning1,323,125,00072,750,0006,650,00079,400,000⁦6%⁩
Total26,462,500,0007,392,250,000546,750,0007,939,000,000⁦30%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Anas Al-Sheikh

Al-Sheikh⁦2025-11-19⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2025-11-21⁩

Project manager

Eng. Qasem Al-Hariri

Al-Hariri⁦2025-11-24⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2025-11-27⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2025-11-30⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-11-19⁩

    Eng. Anas Al-Sheikh

  2. Engineer verifies quantities⁦2025-11-21⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2025-11-24⁩

    Eng. Qasem Al-Hariri · Director, Transport & Housing Projects

    Took 3 days

  4. Payment order prepared⁦2025-11-27⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-11-30⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeLate · ⁦2026-01-13⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Qasem Al-Hariri → Dr. Samer Al-Daqqar

Certificate history

30 November 2025

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2025-11-30 13:00

27 November 2025

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2025-11-27 13:00

24 November 2025

  1. Approval: Eng. Qasem Al-Hariri signed “Project manager certifies”

    2025-11-24 13:00

21 November 2025

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2025-11-21 13:00

19 November 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-11-19 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close