Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Certificate ⁦17⁩ — September 2025

Darayya replacement housing — construction

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
17
Date
⁦2025-10-18⁩
Reference
PAY-2024-011-17

Interim payment certificate no. (⁦17⁩)

For the work of September 2025

Contract number
PSA/2024/011
Tender file no.
2401780147
Contract
Darayya replacement housing — construction
Contractor
Al-Bunyan Al-Mateen Contracting Co.
Contractor tax number
TX-403137
Project
Darayya Replacement Housing
Contract period
⁦2024-04-01⁩ — ⁦2027-06-30⁩
Original contract value
SYP25,500,000,000
Current contract value
SYP26,462,500,000including variations of SYP 962.5M
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SYP)

1Total value of work completed to date7,392,250,000
2Less: previous certificates(6,918,250,000)
3Value of work in this certificate474,000,000
4Less: retention (⁦10%⁩)(47,400,000)
5Less: advance payment recovery (⁦10%⁩)(47,400,000)
6Less: delay and breach penalties0
7Total deductions(94,800,000)
8Net amount payable to the contractorSYP379,200,000

Amount in words: Three hundred seventy-nine million two hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 739.2M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation1,852,375,0001,123,600,00070,250,0001,193,850,000⁦64%⁩
Earthworks & foundations4,763,250,0001,750,650,000112,200,0001,862,850,000⁦39%⁩
Concrete & structural works8,203,375,0002,358,400,000162,350,0002,520,750,000⁦31%⁩
Mechanical, electrical & plumbing6,351,000,0001,155,000,00086,900,0001,241,900,000⁦20%⁩
Finishes & external works3,969,375,000462,325,00036,650,000498,975,000⁦13%⁩
Testing & commissioning1,323,125,00068,275,0005,650,00073,925,000⁦6%⁩
Total26,462,500,0006,918,250,000474,000,0007,392,250,000⁦28%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Anas Al-Sheikh

Al-Sheikh⁦2025-10-18⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2025-10-20⁩

Project manager

Eng. Qasem Al-Hariri

Al-Hariri⁦2025-10-23⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2025-10-26⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2025-10-29⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-10-18⁩

    Eng. Anas Al-Sheikh

  2. Engineer verifies quantities⁦2025-10-20⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2025-10-23⁩

    Eng. Qasem Al-Hariri · Director, Transport & Housing Projects

    Took 3 days

  4. Payment order prepared⁦2025-10-26⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-10-29⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeLate · ⁦2026-01-13⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Qasem Al-Hariri → Dr. Samer Al-Daqqar

Certificate history

29 October 2025

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2025-10-29 13:00

26 October 2025

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2025-10-26 13:00

23 October 2025

  1. Approval: Eng. Qasem Al-Hariri signed “Project manager certifies”

    2025-10-23 13:00

20 October 2025

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2025-10-20 13:00

18 October 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-10-18 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close