AI insight
Al-Bunyan Al-Mateen Contracting Co.’s index fell 13 points in a year
Weakest on Schedule adherence, while holding SYP 38.8B of live contracts. A written corrective plan and a monthly review are advised before any new award.
Grade 1 — Buildings & public facilities
Entity average 77
of 3 contracts on 3 projects
Paid across all its contracts: SYP 15.7B
of 3 logged
SYP 362.5M
The seven axes the vendor is rated on each quarter, and its index across all its projects against the entity average.
Latest evaluation: Q3 2026 · 2026-10-05
| Category | Al-Bunyan Al-Mateen Contracting Co. | Entity average |
|---|---|---|
| Quality | 72 | 80 |
| Delivery | 60 | 74 |
| Schedule adherence | 54 | 70 |
| Compliance | 74 | 81 |
| Safety | 70 | 85 |
| Responsiveness | 62 | 74 |
| Financial standing | 66 | 75 |
Change since the Q2 2026 evaluation
Vendor performance index across its projects
Eight quarters, against the entity average and the target
AI insight
Weakest on Schedule adherence, while holding SYP 38.8B of live contracts. A written corrective plan and a monthly review are advised before any new award.
Every contract of the vendor with its own performance and its project’s health — the index is built from these.
PSA/2024/011In progress
Darayya replacement housing — construction
Darayya Replacement HousingOff track
Performance
PSA/2024/017In progress
Douma wastewater treatment plant — construction
Douma Wastewater Treatment PlantOff track
Performance
PSA/2025/025In progress
Maarat al-Numan roads, water & drainage — rehabilitation works
Maarat al-Numan Infrastructure Rehabilitation — with Idlib GovernorateAt risk
Performance
Logged: 3 · open: 2
Updated programme submitted late
DelayMedium2026-10-09PSA/2025/025
Under-strength concrete in the axis 9 columns
QualityHigh2026-09-03PSA/2024/017
Work at height without fall protection in zone 3 of the site
SafetyHigh2026-08-14PSA/2024/011
Vendor risks, contractual risks on its projects, and its open claims
120-day extension claim with compensation
High · Eng. Qasem Al-Hariri
Contractor claim for a 120-day extension with compensation
RSK-0017 · Darayya Replacement Housing
120-day extension with compensation — utility relocation
Extension of time · In review
Registration and compliance documents with their expiry, contact details and the evaluation history.
Documents expiring within 60 days: 1
| Document | Number | Expiry | |
|---|---|---|---|
| Commercial registration | س.ت دمشق 24873 | 2027-02-15Expires in 110 days | |
| Tax clearance certificate | TX-403137 | 2028-12-31Expires in 795 days | |
| Certified financial statement | FC-2026-41113 | 2027-04-30Expires in 184 days | |
| Social-insurance clearance | SI-880977 | 2027-01-31Expires in 95 days | |
| Not-debarred certificate | ND-52061 | 2027-03-31Expires in 154 days | |
| Professional union membership | PU-310211 | 2027-06-30Expires in 245 days | |
| Contractor classification | CL-7417 | 2027-08-31Expires in 307 days | |
| ISO 9001 certificate | ISO9001-20389 | 2026-12-20Expires in 53 days |
Account contact
Eng. Anas Al-Sheikh
Projects Director
Quarterly evaluation by the project manager or finance
Q3 2026
2026-10-05 · Eng. Wael Al-Khawlani
Q2 2026
2026-07-01 · Eng. Wael Al-Khawlani
Q1 2026
2026-04-01 · Eng. Wael Al-Khawlani
Q4 2025
2026-01-01 · Eng. Wael Al-Khawlani
Impediment: Eng. Wael Al-Khawlani logged a violation Updated programme submitted late
2026-10-09 09:00Edit: Eng. Wael Al-Khawlani evaluated the vendor for Q3 2026
2026-10-05 10:00Impediment: Eng. Wael Al-Khawlani logged a violation Under-strength concrete in the axis 9 columns
2026-09-03 09:00Impediment: Eng. Wael Al-Khawlani logged a violation Work at height without fall protection in zone 3 of the site
2026-08-14 09:00Edit: Eng. Wael Al-Khawlani evaluated the vendor for Q2 2026
2026-07-01 10:00Edit: Eng. Wael Al-Khawlani evaluated the vendor for Q1 2026
2026-04-01 10:00