Certificate ⁦20⁩ — January 2026

Darayya replacement housing — construction

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
20
Date
⁦2026-01-23⁩
Reference
PAY-2024-011-20

Interim payment certificate no. (⁦20⁩)

For the work of January 2026

Contract number
PSA/2024/011
Tender file no.
2401780147
Contract
Darayya replacement housing — construction
Contractor
Al-Bunyan Al-Mateen Contracting Co.
Contractor tax number
TX-403137
Project
Darayya Replacement Housing
Contract period
⁦2024-04-01⁩ — ⁦2027-06-30⁩
Original contract value
SYP25,500,000,000
Current contract value
SYP26,462,500,000including variations of SYP 962.5M
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SYP)

1Total value of work completed to date8,801,750,000
2Less: previous certificates(8,380,000,000)
3Value of work in this certificate421,750,000
4Less: retention (⁦10%⁩)(42,175,000)
5Less: advance payment recovery (⁦10%⁩)(42,175,000)
6Less: delay and breach penalties0
7Total deductions(84,350,000)
8Net amount payable to the contractorSYP337,400,000

Amount in words: Three hundred thirty-seven million four hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 880.2M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation1,852,375,0001,360,350,00061,100,0001,421,450,000⁦77%⁩
Earthworks & foundations4,763,250,0002,119,825,00098,225,0002,218,050,000⁦47%⁩
Concrete & structural works8,203,375,0002,856,800,000144,600,0003,001,400,000⁦37%⁩
Mechanical, electrical & plumbing6,351,000,0001,399,775,00078,925,0001,478,700,000⁦23%⁩
Finishes & external works3,969,375,000560,475,00033,650,000594,125,000⁦15%⁩
Testing & commissioning1,323,125,00082,775,0005,250,00088,025,000⁦7%⁩
Total26,462,500,0008,380,000,000421,750,0008,801,750,000⁦33%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Anas Al-Sheikh

Al-Sheikh⁦2026-01-23⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-01-25⁩

Project manager

Eng. Qasem Al-Hariri

Al-Hariri⁦2026-01-28⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-01-31⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-02-03⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-01-23⁩

    Eng. Anas Al-Sheikh

  2. Engineer verifies quantities⁦2026-01-25⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-01-28⁩

    Eng. Qasem Al-Hariri · Director, Transport & Housing Projects

    Took 3 days

  4. Payment order prepared⁦2026-01-31⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-02-03⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeLate · ⁦2026-01-13⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Qasem Al-Hariri → Dr. Samer Al-Daqqar

Certificate history

3 February 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-02-03 13:00

31 January 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-01-31 13:00

28 January 2026

  1. Approval: Eng. Qasem Al-Hariri signed “Project manager certifies”

    2026-01-28 13:00

25 January 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-01-25 13:00

23 January 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-01-23 09:00