Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 6
- Date
- 2024-10-25
- Reference
- PAY-2024-011-06
Interim payment certificate no. (6)
For the work of October 2024
- Contract number
- PSA/2024/011
- Tender file no.
- 2401780147
- Contract
- Darayya replacement housing — construction
- Contractor
- Al-Bunyan Al-Mateen Contracting Co.
- Contractor tax number
- TX-403137
- Project
- Darayya Replacement Housing
- Contract period
- 2024-04-01 — 2027-06-30
- Original contract value
- SYP25,500,000,000
- Current contract value
- SYP26,462,500,000including variations of SYP 962.5M
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SYP)
| 1 | Total value of work completed to date | 1,695,250,000 |
| 2 | Less: previous certificates | (1,331,750,000) |
| 3 | Value of work in this certificate | 363,500,000 |
| 4 | Less: retention (10%) | (36,350,000) |
| 5 | Less: advance payment recovery (10%) | (36,350,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (72,700,000) |
| 8 | Net amount payable to the contractor | SYP290,800,000 |
Amount in words: Two hundred ninety million eight hundred thousand Syrian pounds only
Retention held up to this certificate: SYP 169.5M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 1,852,375,000 | 216,025,000 | 57,775,000 | 273,800,000 | 15% |
| Earthworks & foundations | 4,763,250,000 | 336,675,000 | 90,525,000 | 427,200,000 | 9% |
| Concrete & structural works | 8,203,375,000 | 454,025,000 | 124,050,000 | 578,075,000 | 7% |
| Mechanical, electrical & plumbing | 6,351,000,000 | 222,650,000 | 62,150,000 | 284,800,000 | 4% |
| Finishes & external works | 3,969,375,000 | 89,200,000 | 25,225,000 | 114,425,000 | 3% |
| Testing & commissioning | 1,323,125,000 | 13,175,000 | 3,775,000 | 16,950,000 | 1% |
| Total | 26,462,500,000 | 1,331,750,000 | 363,500,000 | 1,695,250,000 | 6% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Anas Al-Sheikh
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. Qasem Al-Hariri
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar