Certificate ⁦10⁩ — February 2025

Darayya replacement housing — construction

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
10
Date
⁦2025-03-04⁩
Reference
PAY-2024-011-10

Interim payment certificate no. (⁦10⁩)

For the work of February 2025

Contract number
PSA/2024/011
Tender file no.
2401780147
Contract
Darayya replacement housing — construction
Contractor
Al-Bunyan Al-Mateen Contracting Co.
Contractor tax number
TX-403137
Project
Darayya Replacement Housing
Contract period
⁦2024-04-01⁩ — ⁦2027-06-30⁩
Original contract value
SYP25,500,000,000
Current contract value
SYP26,462,500,000including variations of SYP 962.5M
Linked milestone
Earthworks & foundations complete · MS-G2 Designs approved

Certificate summary (SYP)

1Total value of work completed to date3,662,500,000
2Less: previous certificates(3,090,500,000)
3Value of work in this certificate572,000,000
4Less: retention (⁦10%⁩)(57,200,000)
5Less: advance payment recovery (⁦10%⁩)(57,200,000)
6Less: delay and breach penalties0
7Total deductions(114,400,000)
8Net amount payable to the contractorSYP457,600,000

Amount in words: Four hundred fifty-seven million six hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 366.3M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation1,852,375,000502,450,00089,025,000591,475,000⁦32%⁩
Earthworks & foundations4,763,250,000782,675,000140,275,000922,950,000⁦19%⁩
Concrete & structural works8,203,375,0001,053,500,000195,425,0001,248,925,000⁦15%⁩
Mechanical, electrical & plumbing6,351,000,000515,325,00099,975,000615,300,000⁦10%⁩
Finishes & external works3,969,375,000206,125,00041,100,000247,225,000⁦6%⁩
Testing & commissioning1,323,125,00030,425,0006,200,00036,625,000⁦3%⁩
Total26,462,500,0003,090,500,000572,000,0003,662,500,000⁦14%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Anas Al-Sheikh

Al-Sheikh⁦2025-03-04⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2025-03-06⁩

Project manager

Eng. Qasem Al-Hariri

Al-Hariri⁦2025-03-09⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2025-03-12⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2025-03-15⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-03-04⁩

    Eng. Anas Al-Sheikh

  2. Engineer verifies quantities⁦2025-03-06⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2025-03-09⁩

    Eng. Qasem Al-Hariri · Director, Transport & Housing Projects

    Took 3 days

  4. Payment order prepared⁦2025-03-12⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-03-15⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneEarthworks & foundations completeDone · ⁦2025-02-27⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2026-05-07⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Qasem Al-Hariri → Dr. Samer Al-Daqqar

Certificate history

15 March 2025

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2025-03-15 13:00

12 March 2025

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2025-03-12 13:00

9 March 2025

  1. Approval: Eng. Qasem Al-Hariri signed “Project manager certifies”

    2025-03-09 13:00

6 March 2025

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2025-03-06 13:00

4 March 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-03-04 09:00