Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 8
- Date
- 2024-12-29
- Reference
- PAY-2024-011-08
Interim payment certificate no. (8)
For the work of December 2024
- Contract number
- PSA/2024/011
- Tender file no.
- 2401780147
- Contract
- Darayya replacement housing — construction
- Contractor
- Al-Bunyan Al-Mateen Contracting Co.
- Contractor tax number
- TX-403137
- Project
- Darayya Replacement Housing
- Contract period
- 2024-04-01 — 2027-06-30
- Original contract value
- SYP25,500,000,000
- Current contract value
- SYP26,462,500,000including variations of SYP 962.5M
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SYP)
| 1 | Total value of work completed to date | 2,618,500,000 |
| 2 | Less: previous certificates | (2,170,250,000) |
| 3 | Value of work in this certificate | 448,250,000 |
| 4 | Less: retention (10%) | (44,825,000) |
| 5 | Less: advance payment recovery (10%) | (44,825,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (89,650,000) |
| 8 | Net amount payable to the contractor | SYP358,600,000 |
Amount in words: Three hundred fifty-eight million six hundred thousand Syrian pounds only
Retention held up to this certificate: SYP 261.9M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 1,852,375,000 | 352,350,000 | 70,575,000 | 422,925,000 | 23% |
| Earthworks & foundations | 4,763,250,000 | 549,000,000 | 110,850,000 | 659,850,000 | 14% |
| Concrete & structural works | 8,203,375,000 | 739,850,000 | 153,050,000 | 892,900,000 | 11% |
| Mechanical, electrical & plumbing | 6,351,000,000 | 362,500,000 | 77,400,000 | 439,900,000 | 7% |
| Finishes & external works | 3,969,375,000 | 145,150,000 | 31,600,000 | 176,750,000 | 4% |
| Testing & commissioning | 1,323,125,000 | 21,400,000 | 4,775,000 | 26,175,000 | 2% |
| Total | 26,462,500,000 | 2,170,250,000 | 448,250,000 | 2,618,500,000 | 10% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Anas Al-Sheikh
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. Qasem Al-Hariri
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar