Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 13
- Date
- 2025-06-10
- Reference
- PAY-2024-011-13
Interim payment certificate no. (13)
For the work of May 2025
- Contract number
- PSA/2024/011
- Tender file no.
- 2401780147
- Contract
- Darayya replacement housing — construction
- Contractor
- Al-Bunyan Al-Mateen Contracting Co.
- Contractor tax number
- TX-403137
- Project
- Darayya Replacement Housing
- Contract period
- 2024-04-01 — 2027-06-30
- Original contract value
- SYP25,500,000,000
- Current contract value
- SYP26,462,500,000including variations of SYP 962.5M
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 5,297,500,000 |
| 2 | Less: previous certificates | (4,705,750,000) |
| 3 | Value of work in this certificate | 591,750,000 |
| 4 | Less: retention (10%) | (59,175,000) |
| 5 | Less: advance payment recovery (10%) | (59,175,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (118,350,000) |
| 8 | Net amount payable to the contractor | SYP473,400,000 |
Amount in words: Four hundred seventy-three million four hundred thousand Syrian pounds only
Retention held up to this certificate: SYP 529.8M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 1,852,375,000 | 765,275,000 | 90,275,000 | 855,550,000 | 46% |
| Earthworks & foundations | 4,763,250,000 | 1,191,925,000 | 143,050,000 | 1,334,975,000 | 28% |
| Concrete & structural works | 8,203,375,000 | 1,604,075,000 | 202,375,000 | 1,806,450,000 | 22% |
| Mechanical, electrical & plumbing | 6,351,000,000 | 784,475,000 | 105,500,000 | 889,975,000 | 14% |
| Finishes & external works | 3,969,375,000 | 313,750,000 | 43,825,000 | 357,575,000 | 9% |
| Testing & commissioning | 1,323,125,000 | 46,250,000 | 6,725,000 | 52,975,000 | 4% |
| Total | 26,462,500,000 | 4,705,750,000 | 591,750,000 | 5,297,500,000 | 20% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Anas Al-Sheikh
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. Qasem Al-Hariri
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar