RSK-0016Darayya Replacement Housing
Late hand-over of the northern plot and utility diversions in blocks 3 and 4
A risk's detail, response, contingency and residual risk.
Risk statement
From cause to event to impact — with the preventive controls before the event and the contingency after it
Cause
Late handover of the northern part of the site, and utility diversions in blocks 3 and 4
Preventive controls
- A joint committee with the electricity transmission & distribution establishment and Rif Dimashq Governorate to schedule the diversions
- Re-sequence works to start with blocks 1 and 2
1 / 2
Event
Late hand-over of the northern plot and utility diversions in blocks 3 and 4
No part of the land handed over before the end of November
Contingency
Move laydown areas and site offices to block 2 until the land is fully handed over
Impact
Blocks 3 and 4 and their networks at least 75 days late, and extension claims from the contractor
Assessment
The level before and after the response
Inherent
Residual
Exposure
SYP 775M
Residual
40% off the score
Score trend
Last six months
- Score
- Target residual
Escalation path
Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director
Last reviewed 4 days ago
Project manager
Eng. Qasem Al-Hariri
Currently followed up hereProgramme manager
Current levelEng. Qasem Al-Hariri
Automatically at 15 days unreviewed · in 11 days- 3
PMO director
Dr. Reem Al-Qabbani
Automatically at 20 days unreviewed · in 16 days - 4
Executive Council
Dr. Samer Al-Daqqar
By the PMO director’s decision
Mitigation plan
Each action with its owner and date — tick it off when complete
A joint committee with the electricity transmission & distribution establishment and Rif Dimashq Governorate to schedule the diversions
Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.syIn progressIn 8 days2026-11-05Re-sequence works to start with blocks 1 and 2
Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syDone2026-10-152026-10-15
Trigger
No part of the land handed over before the end of November
Contingency
Move laydown areas and site offices to block 2 until the land is fully handed over