RSK-0016Darayya Replacement Housing

Late hand-over of the northern plot and utility diversions in blocks 3 and 4

20CriticalEscalatedMaterial

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Late handover of the northern part of the site, and utility diversions in blocks 3 and 4

Preventive controls

  • A joint committee with the electricity transmission & distribution establishment and Rif Dimashq Governorate to schedule the diversions
  • Re-sequence works to start with blocks 1 and 2

1 / 2

Event

Late hand-over of the northern plot and utility diversions in blocks 3 and 4

20CriticalTrigger

No part of the land handed over before the end of November

Contingency

Move laydown areas and site offices to block 2 until the land is fully handed over

Impact

Blocks 3 and 4 and their networks at least 75 days late, and extension claims from the contractor

SYP 775M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
20Critical

Residual

5
4
3
2
1
1
2
3
4
5
12Medium

Exposure

SYP 775M

Residual

⁦40⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 4 days ago

  1. Project manager

    Eng. Qasem Al-Hariri

    Currently followed up here
  2. Programme manager

    Current level

    Eng. Qasem Al-Hariri

    Automatically at 15 days unreviewed · in 11 days
  3. 3

    PMO director

    Dr. Reem Al-Qabbani

    Automatically at 20 days unreviewed · in 16 days
  4. 4

    Executive Council

    Dr. Samer Al-Daqqar

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦1⁩ of ⁦2⁩ done
  • A joint committee with the electricity transmission & distribution establishment and Rif Dimashq Governorate to schedule the diversions

    Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy
    In progressIn 8 days2026-11-05
  • Re-sequence works to start with blocks 1 and 2

    Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy
    Done2026-10-152026-10-15

Trigger

No part of the land handed over before the end of November

Contingency

Move laydown areas and site offices to block 2 until the land is fully handed over