Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

RSK-0015Darayya Replacement Housing

Steel and concrete price rises driving price-adjustment claims

20CriticalEscalatedMaterial

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Steel up 22% and ready-mix concrete up 15% since award

Preventive controls

  • Apply the price-adjustment formula in the tender book
  • Negotiate advance purchase of the remaining steel

2 / 2

Event

Steel and concrete price rises driving price-adjustment claims

20CriticalTrigger

Approved claims above SYP 750M

Contingency

Fund the gap from the 2027 investment-plan reserve by decision of the national steering committee

Impact

Price-adjustment claims near SYP 1.2bn, above the project contingency

SYP 1.2B

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
20Critical

Residual

5
4
3
2
1
1
2
3
4
5
12Medium

Exposure

SYP 1.2B

Residual

⁦40⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 4 days ago

  1. Project manager

    Eng. Qasem Al-Hariri

    Currently followed up here
  2. Programme manager

    Current level

    Eng. Qasem Al-Hariri

    Automatically at 15 days unreviewed · in 11 days
  3. 3

    PMO director

    Dr. Reem Al-Qabbani

    Automatically at 20 days unreviewed · in 16 days
  4. 4

    Executive Council

    Dr. Samer Al-Daqqar

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦0⁩ of ⁦2⁩ done
  • Apply the price-adjustment formula in the tender book

    Omar Al-NahhasOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.sy
    In progressIn 13 days2026-11-10
  • Negotiate advance purchase of the remaining steel

    Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy
    In progressIn 18 days2026-11-15

Trigger

Approved claims above SYP 750M

Contingency

Fund the gap from the 2027 investment-plan reserve by decision of the national steering committee

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close