Darayya Replacement Housing
Remove from watchlistReplacement housing for families returning to Darayya — four linked residential blocks with water, power and internal roads, a school and a health centre, on land allocated by Rif Dimashq Governorate.
Budget (BAC)
Actual cost
45% of budget
Progress
Estimate at completion
+SYP 2.2B
SPI · CPI
Forecast finish
74 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure25 March 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 January 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate3 March 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate13 September 2024Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate25 March 2027Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2024-11-09 | 2025-05-27 | +199 days | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-05-20 | 2026-05-07 | +352 days | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-03-05 | 2027-01-17 | +318 days | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-12-19 | 2027-06-19 | +182 days | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-06-30 | 2027-09-29 | +91 days | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
42%Awaiting acceptance
11%Not handed in
47%Deliverable flow
Display options
| Project plan & baseline002-D1 | 4% | CRT-002-01 | Approved | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy | Eng. Wassim Al-Azm | 2024-08-04 | V1 | 3 of 3 |
| Monitoring & reporting002-D2 | 4% | CRT-002-02 | Approved | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2024-11-09 | V1 | 3 of 3 |
| Detailed design002-D3 | 8% | CRT-002-03 | Approved | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2025-02-13 | V1 | 3 of 3 |
| Permits & approvals002-D4 | 8% | CRT-002-04 | Approved | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Eng. Wassim Al-Azm | 2025-05-20 | V1 | 3 of 3 |
| Site works & excavation002-D5 | 18% | CRT-002-05 | Approved | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Eng. Wassim Al-Azm | 2025-08-25 | V1 | 3 of 3 |
| Structure002-D6 | 11% | — | Under review | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy | Eng. Wassim Al-Azm | 2025-11-29 | V1 | 1 of 3 |
| Finishes002-D7 | 11% | — | Draft | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2026-03-05 | V0 | 0 of 3 |
| Supply002-D8 | 8% | — | Draft | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy | Eng. Wassim Al-Azm | 2026-06-10 | V0 | 0 of 3 |
| Installation002-D9 | 8% | — | Draft | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2026-09-14 | V0 | 0 of 3 |
| Testing & commissioning002-D10 | 8% | — | Draft | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Eng. Wassim Al-Azm | 2026-12-19 | V0 | 0 of 3 |
| Provisional acceptance002-D11 | 6% | — | Draft | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2027-03-26 | V0 | 0 of 3 |
| Final acceptance002-D12 | 6% | — | Draft | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Eng. Wassim Al-Azm | 2027-06-30 | V0 | 0 of 3 |
| Total · 12 | 100% |