Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-002Off track4ExecutionConstructionStalledDelivered by:Ministry of Public Works and Housing

Darayya Replacement Housing

Remove from watchlist

Replacement housing for families returning to Darayya — four linked residential blocks with water, power and internal roads, a school and a health centre, on land allocated by Rif Dimashq Governorate.

Early warning: ⁦88%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SYP 29.5B

Actual cost

SYP 13.3B

⁦45%⁩ of budget

Progress

⁦42%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 31.7B

+SYP 2.2B

SPI · CPI

0.82Schedule performance index · 0.820.93Cost performance index · 0.93

Forecast finish

⁦2027-09-12⁩

74 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure25 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 January 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 March 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate13 September 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate25 March 2027Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
PSA-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2026-05-07⁩
ApprovedCRT-002-04Permits & approvals

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-002
Project
Darayya Replacement Housing
Portfolio
Reconstruction & Infrastructure Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Qasem Al-Hariri

1The deliverableAuto-filled

DeliverableAuto-filled
Permits & approvals
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Salma Al-Zaim
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦8%⁩
DueAuto-filled
⁦2025-05-20⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-002_2.2_v1.pdfV1Salma Al-Zaim⁦2025-08-04⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Eng. Wassim Al-Azm
Accepted byAuto-filled
Salma Al-Zaim
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Designs approved
ContractAuto-filled
CTR-2024-011
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Salma Al-ZaimDeputy President, Finance, Administration & the Investment PlanSubmitted—⁦2025-08-04⁩ 09:18
2Evidence against the acceptance criteriaMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2025-08-05⁩ 13:34
3Inspection & technical acceptance — ownerTechnical acceptanceSalma Al-ZaimProject ownerOn behalf of Eng. Wassim Al-AzmApprovedInspected and accepted against the approved acceptance criteria.⁦2025-08-10⁩ 14:41
4Deliverable matched to the contract lineFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2025-08-12⁩ 12:33
5Certificate linked to the payment certificateFinancial approvalRasha Al-MudarresFinanceApproved—⁦2025-08-13⁩ 13:10

Signatures

Evidence against the acceptance criteria

Mariam Al-Zoubi

Approved⁦2025-08-05⁩

Inspection & technical acceptance — owner

Salma Al-Zaim

Approved⁦2025-08-10⁩

Deliverable matched to the contract line

Abdullah Al-Ujaili

Approved⁦2025-08-12⁩

Certificate linked to the payment certificate

Rasha Al-Mudarres

Approved⁦2025-08-13⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Salma Al-Zaim on ⁦2025-08-04⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2025-08-05⁩ at ⁦13:34⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Eng. Wassim Al-Azm · Project owner

    Approved · ⁦2025-08-10⁩ at ⁦14:41⁩ · On behalf of Eng. Wassim Al-Azm (Salma Al-Zaim)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-08-12⁩ at ⁦12:33⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2025-08-13⁩ at ⁦13:10⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-08-04⁩

    PRJ-2026-002_2.2_v1.pdf

    Salma Al-Zaim

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close