RSK-0017Darayya Replacement Housing

Contractor claim for a 120-day extension with compensation

16HighOpenMaterial

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Approved variations with no matching time extension, and late handover of parts of the site

Preventive controls

  • An independent time-impact analysis of the claim

1 / 1

Event

Contractor claim for a 120-day extension with compensation

16HighTrigger

The contractor rejects the independent analysis

Contingency

Refer the claim to the dispute committee named in the contract

Impact

A 120-day extension claim with compensation up to SYP 462.5M

SYP 462.5M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
16High

Residual

5
4
3
2
1
1
2
3
4
5
9Medium

Exposure

SYP 462.5M

Residual

⁦44⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 8 days ago

  1. Project manager

    Current level

    Eng. Qasem Al-Hariri

    Currently followed up here
  2. 2

    Programme manager

    Eng. Qasem Al-Hariri

    Automatically at 15 days unreviewed · in 7 days
  3. 3

    PMO director

    Dr. Reem Al-Qabbani

    Automatically at 20 days unreviewed · in 12 days
  4. 4

    Executive Council

    Dr. Samer Al-Daqqar

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦0⁩ of ⁦1⁩ done
  • An independent time-impact analysis of the claim

    Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy
    In progressIn 23 days2026-11-20

Trigger

The contractor rejects the independent analysis

Contingency

Refer the claim to the dispute committee named in the contract

Esc