Certificate ⁦14⁩ — July 2026

Supply & install lighting, cameras, smart signals and the control room — southern M5

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
14
Date
⁦2026-08-09⁩
Reference
PAY-2026-003

Interim payment certificate no. (⁦14⁩)

For the work of July 2026

Contract number
PSA/2025/002
Tender file no.
2503250420
Contract
Supply & install lighting, cameras, smart signals and the control room — southern M5
Contractor
Modern Networks Telecom Co.
Contractor tax number
TX-409411
Project
Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals
Contract period
⁦2025-03-02⁩ — ⁦2026-10-31⁩
Original contract value
SYP1,537,500,000
Current contract value
SYP1,537,500,000
Linked milestone
Testing & commissioning · MS-G5 Final handover

Certificate summary (SYP)

1Total value of work completed to date1,255,000,000
2Less: previous certificates(1,172,500,000)
3Value of work in this certificate82,500,000
4Less: retention (⁦10%⁩)(8,250,000)
5Less: advance payment recovery (⁦10%⁩)(8,250,000)
6Less: delay and breach penalties0
7Total deductions(16,500,000)
8Net amount payable to the contractorSYP66,000,000

Amount in words: Sixty-six million Syrian pounds only

Retention held up to this certificate: SYP 125.5M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation107,625,000104,025,0003,600,000107,625,000⁦100%⁩
Earthworks & foundations276,750,000265,525,00011,225,000276,750,000⁦100%⁩
Concrete & structural works476,625,000446,925,00029,700,000476,625,000⁦100%⁩
Mechanical, electrical & plumbing369,000,000269,625,00027,100,000296,725,000⁦80%⁩
Finishes & external works230,625,00075,450,0009,275,00084,725,000⁦37%⁩
Testing & commissioning76,875,00010,950,0001,600,00012,550,000⁦16%⁩
Total1,537,500,0001,172,500,00082,500,0001,255,000,000⁦82%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Ammar Al-Ahmad

Al-Ahmad⁦2026-08-09⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-08-11⁩

Project manager

Eng. Maher Al-Hamawi

Al-Hamawi⁦2026-08-14⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-08-17⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-08-20⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-08-09⁩

    Eng. Ammar Al-Ahmad

  2. Engineer verifies quantities⁦2026-08-11⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-08-14⁩

    Eng. Maher Al-Hamawi · Director, Energy, Water & Utilities Projects

    Took 3 days

  4. Payment order prepared⁦2026-08-17⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-08-20⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneTesting & commissioningLate · ⁦2026-09-12⁩
  2. Project milestoneMS-G5Final handoverMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Maher Al-Hamawi → Dr. Samer Al-Daqqar

Certificate history

20 August 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-08-20 13:00

17 August 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-08-17 13:00

14 August 2026

  1. Approval: Eng. Maher Al-Hamawi signed “Project manager certifies”

    2026-08-14 13:00

11 August 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-08-11 13:00

9 August 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-08-09 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close