Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Certificate ⁦13⁩ — June 2026

Supply & install lighting, cameras, smart signals and the control room — southern M5

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
13
Date
⁦2026-07-08⁩
Reference
PAY-2025-002-13

Interim payment certificate no. (⁦13⁩)

For the work of June 2026

Contract number
PSA/2025/002
Tender file no.
2503250420
Contract
Supply & install lighting, cameras, smart signals and the control room — southern M5
Contractor
Modern Networks Telecom Co.
Contractor tax number
TX-409411
Project
Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals
Contract period
⁦2025-03-02⁩ — ⁦2026-10-31⁩
Original contract value
SYP1,537,500,000
Current contract value
SYP1,537,500,000
Linked milestone
MEP systems installed · MS-G4 Testing & acceptance complete

Certificate summary (SYP)

1Total value of work completed to date1,172,500,000
2Less: previous certificates(1,129,000,000)
3Value of work in this certificate43,500,000
4Less: retention (⁦10%⁩)(4,350,000)
5Less: advance payment recovery (⁦10%⁩)(4,350,000)
6Less: delay and breach penalties0
7Total deductions(8,700,000)
8Net amount payable to the contractorSYP34,800,000

Amount in words: Thirty-four million eight hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 117.3M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation107,625,000105,275,0002,350,000107,625,000⁦100%⁩
Earthworks & foundations276,750,000269,725,0007,025,000276,750,000⁦100%⁩
Concrete & structural works476,625,000459,300,00017,325,000476,625,000⁦100%⁩
Mechanical, electrical & plumbing369,000,000209,400,00011,225,000220,625,000⁦60%⁩
Finishes & external works230,625,00074,400,0004,750,00079,150,000⁦34%⁩
Testing & commissioning76,875,00010,900,000825,00011,725,000⁦15%⁩
Total1,537,500,0001,129,000,00043,500,0001,172,500,000⁦76%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Ammar Al-Ahmad

Al-Ahmad⁦2026-07-08⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-07-10⁩

Project manager

Eng. Maher Al-Hamawi

Al-Hamawi⁦2026-07-13⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-07-16⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-07-19⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-07-08⁩

    Eng. Ammar Al-Ahmad

  2. Engineer verifies quantities⁦2026-07-10⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-07-13⁩

    Eng. Maher Al-Hamawi · Director, Energy, Water & Utilities Projects

    Took 3 days

  4. Payment order prepared⁦2026-07-16⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-07-19⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMEP systems installedDone · ⁦2026-06-19⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone not approved yet

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Maher Al-Hamawi → Dr. Samer Al-Daqqar

Certificate history

19 July 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-07-19 13:00

16 July 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-07-16 13:00

13 July 2026

  1. Approval: Eng. Maher Al-Hamawi signed “Project manager certifies”

    2026-07-13 13:00

10 July 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-07-10 13:00

8 July 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-07-08 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close