Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Certificate ⁦2⁩ — May 2025

Supply & install lighting, cameras, smart signals and the control room — southern M5

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
2
Date
⁦2025-05-23⁩
Reference
PAY-2025-002-02

Interim payment certificate no. (⁦2⁩)

For the work of May 2025

Contract number
PSA/2025/002
Tender file no.
2503250420
Contract
Supply & install lighting, cameras, smart signals and the control room — southern M5
Contractor
Modern Networks Telecom Co.
Contractor tax number
TX-409411
Project
Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals
Contract period
⁦2025-03-02⁩ — ⁦2026-10-31⁩
Original contract value
SYP1,537,500,000
Current contract value
SYP1,537,500,000
Linked milestone
Earthworks & foundations complete · MS-G2 Designs approved

Certificate summary (SYP)

1Total value of work completed to date111,000,000
2Less: previous certificates(43,000,000)
3Value of work in this certificate68,000,000
4Less: retention (⁦10%⁩)(6,800,000)
5Less: advance payment recovery (⁦10%⁩)(6,800,000)
6Less: delay and breach penalties0
7Total deductions(13,600,000)
8Net amount payable to the contractorSYP54,400,000

Amount in words: Fifty-four million four hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 11.1M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation107,625,0007,150,00010,775,00017,925,000⁦17%⁩
Earthworks & foundations276,750,00011,075,00016,900,00027,975,000⁦10%⁩
Concrete & structural works476,625,00014,650,00023,200,00037,850,000⁦8%⁩
Mechanical, electrical & plumbing369,000,0007,000,00011,650,00018,650,000⁦5%⁩
Finishes & external works230,625,0002,750,0004,750,0007,500,000⁦3%⁩
Testing & commissioning76,875,000375,000725,0001,100,000⁦1%⁩
Total1,537,500,00043,000,00068,000,000111,000,000⁦7%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Ammar Al-Ahmad

Al-Ahmad⁦2025-05-23⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2025-05-25⁩

Project manager

Eng. Maher Al-Hamawi

Al-Hamawi⁦2025-05-28⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2025-05-31⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2025-06-03⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-05-23⁩

    Eng. Ammar Al-Ahmad

  2. Engineer verifies quantities⁦2025-05-25⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2025-05-28⁩

    Eng. Maher Al-Hamawi · Director, Energy, Water & Utilities Projects

    Took 3 days

  4. Payment order prepared⁦2025-05-31⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-06-03⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneEarthworks & foundations completeDone · ⁦2025-08-19⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2025-12-10⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Maher Al-Hamawi → Dr. Samer Al-Daqqar

Certificate history

3 June 2025

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2025-06-03 13:00

31 May 2025

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2025-05-31 13:00

28 May 2025

  1. Approval: Eng. Maher Al-Hamawi signed “Project manager certifies”

    2025-05-28 13:00

25 May 2025

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2025-05-25 13:00

23 May 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-05-23 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close