PRJ-2026-013At risk4ExecutionConstructionIn progressDelivered by:Ministry of Transport

Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals

Add to watchlist

Solar lighting for the highway between As-Sanamayn and Daraa: 1,200 lighting poles and traffic cameras, smart signals at the junctions and a traffic control room in Daraa.

Early warning: ⁦58%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 1.9B

Actual cost

SYP 1.6B

⁦84%⁩ of budget

Progress

⁦79%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SYP 2B

+SYP 118.1M

SPI · CPI

0.88Schedule performance index · 0.880.94Cost performance index · 0.94

Forecast finish

⁦2026-12-15⁩

45 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure11 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate18 December 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 February 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate11 September 2026Closure · Not startedClosure · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

3Achieved
0On track
1At risk
1Late
Average delay90 days
Jul 25Oct 25Jan 26Apr 26Jul 26Oct 26Jan 27
Contractual
Build completePlanned: ⁦2026-02-26⁩Forecast / actual: ⁦2026-06-21⁩Delay: 115 daysG3 +115
Executive
Project plan approvedPlanned: ⁦2025-06-24⁩Forecast / actual: ⁦2025-08-03⁩Delay: 40 daysG1 +40
Payment
Final handoverPlanned: ⁦2026-10-31⁩Forecast / actual: ⁦2027-01-11⁩Delay: 72 daysG5 +72
Regulatory
Testing & acceptance completePlanned: ⁦2026-07-24⁩Forecast / actual: ⁦2026-12-22⁩Delay: 151 daysG4 +151
Project
Designs approvedPlanned: ⁦2025-10-01⁩Forecast / actual: ⁦2025-12-10⁩Delay: 70 daysG2 +70

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2025-06-24⁩⁦2025-08-03⁩⁦+40⁩ daysEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.syAchieved1Approved
Designs approvedMS-G2Project⁦2025-10-01⁩⁦2025-12-10⁩⁦+70⁩ daysEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.syAchieved1Approved
Build completeMS-G3Contractual⁦2026-02-26⁩⁦2026-06-21⁩⁦+115⁩ daysEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.syAchieved1Approved
Testing & acceptance completeMS-G4Regulatory⁦2026-07-24⁩⁦2026-12-22⁩⁦+151⁩ daysEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.syLate0Not requested
Final handoverMS-G5Payment⁦2026-10-31⁩⁦2027-01-11⁩⁦+72⁩ daysEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.syAt risk0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦79%⁩

Awaiting acceptance

⁦9%⁩

Not handed in

⁦12%⁩

Deliverable flow

Pick a stage to filter the register
⁦12⁩ results
Export CSV
Project plan & baseline013-D1⁦3%⁩CRT-013-01ApprovedEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.syEng. Wassim Al-Azm⁦2025-05-06⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting013-D2⁦3%⁩CRT-013-02ApprovedEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2025-06-24⁩V1⁦3⁩ of ⁦3⁩
Detailed design013-D3⁦6%⁩CRT-013-03ApprovedEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2025-08-13⁩V1⁦3⁩ of ⁦3⁩
Permits & approvals013-D4⁦6%⁩CRT-013-04ApprovedSalma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.syEng. Wassim Al-Azm⁦2025-10-01⁩V1⁦3⁩ of ⁦3⁩
Site works & excavation013-D5⁦13%⁩CRT-013-05ApprovedSalma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.syEng. Wassim Al-Azm⁦2025-11-19⁩V1⁦3⁩ of ⁦3⁩
Structure013-D6⁦13%⁩CRT-013-06ApprovedEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.syEng. Wassim Al-Azm⁦2026-01-08⁩V1⁦3⁩ of ⁦3⁩
Finishes013-D7⁦13%⁩CRT-013-07ApprovedEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2026-02-26⁩V1⁦3⁩ of ⁦3⁩
Supply013-D8⁦11%⁩CRT-013-08ApprovedEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.syEng. Wassim Al-Azm⁦2026-04-17⁩V1⁦3⁩ of ⁦3⁩
Installation013-D9⁦11%⁩CRT-013-09ApprovedEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2026-06-05⁩V1⁦3⁩ of ⁦3⁩
Testing & commissioning013-D10⁦9%⁩—SubmittedSalma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.syEng. Wassim Al-Azm⁦2026-07-24⁩V1⁦1⁩ of ⁦3⁩
Provisional acceptance013-D11⁦6%⁩—DraftEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2026-09-12⁩V0⁦0⁩ of ⁦3⁩
Final acceptance013-D12⁦6%⁩—DraftSalma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.syEng. Wassim Al-Azm⁦2026-10-31⁩V0⁦0⁩ of ⁦3⁩
Total · 12⁦100%⁩
⁦1⁩–⁦12⁩ of ⁦12⁩