Certificate ⁦8⁩ — December 2025

Supply & install lighting, cameras, smart signals and the control room — southern M5

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
8
Date
⁦2026-01-02⁩
Reference
PAY-2025-002-08

Interim payment certificate no. (⁦8⁩)

For the work of December 2025

Contract number
PSA/2025/002
Tender file no.
2503250420
Contract
Supply & install lighting, cameras, smart signals and the control room — southern M5
Contractor
Modern Networks Telecom Co.
Contractor tax number
TX-409411
Project
Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals
Contract period
⁦2025-03-02⁩ — ⁦2026-10-31⁩
Original contract value
SYP1,537,500,000
Current contract value
SYP1,537,500,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SYP)

1Total value of work completed to date769,250,000
2Less: previous certificates(653,750,000)
3Value of work in this certificate115,500,000
4Less: retention (⁦10%⁩)(11,550,000)
5Less: advance payment recovery (⁦10%⁩)(11,550,000)
6Less: delay and breach penalties0
7Total deductions(23,100,000)
8Net amount payable to the contractorSYP92,400,000

Amount in words: Ninety-two million four hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 76.9M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation107,625,00094,425,00013,200,000107,625,000⁦100%⁩
Earthworks & foundations276,750,000183,125,00027,325,000210,450,000⁦76%⁩
Concrete & structural works476,625,000222,600,00039,725,000262,325,000⁦55%⁩
Mechanical, electrical & plumbing369,000,000105,925,00023,300,000129,225,000⁦35%⁩
Finishes & external works230,625,00041,625,00010,300,00051,925,000⁦23%⁩
Testing & commissioning76,875,0006,050,0001,650,0007,700,000⁦10%⁩
Total1,537,500,000653,750,000115,500,000769,250,000⁦50%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Ammar Al-Ahmad

Al-Ahmad⁦2026-01-02⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-01-04⁩

Project manager

Eng. Maher Al-Hamawi

Al-Hamawi⁦2026-01-07⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-01-10⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-01-13⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-01-02⁩

    Eng. Ammar Al-Ahmad

  2. Engineer verifies quantities⁦2026-01-04⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-01-07⁩

    Eng. Maher Al-Hamawi · Director, Energy, Water & Utilities Projects

    Took 3 days

  4. Payment order prepared⁦2026-01-10⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-01-13⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeDone · ⁦2026-01-30⁩
  2. Project milestoneMS-G3Build completeMilestone approved ⁦2026-06-21⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Maher Al-Hamawi → Dr. Samer Al-Daqqar

Certificate history

13 January 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-01-13 13:00

10 January 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-01-10 13:00

7 January 2026

  1. Approval: Eng. Maher Al-Hamawi signed “Project manager certifies”

    2026-01-07 13:00

4 January 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-01-04 13:00

2 January 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-01-02 09:00