Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 8
- Date
- 2026-01-02
- Reference
- PAY-2025-002-08
Interim payment certificate no. (8)
For the work of December 2025
- Contract number
- PSA/2025/002
- Tender file no.
- 2503250420
- Contract
- Supply & install lighting, cameras, smart signals and the control room — southern M5
- Contractor
- Modern Networks Telecom Co.
- Contractor tax number
- TX-409411
- Project
- Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals
- Contract period
- 2025-03-02 — 2026-10-31
- Original contract value
- SYP1,537,500,000
- Current contract value
- SYP1,537,500,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 769,250,000 |
| 2 | Less: previous certificates | (653,750,000) |
| 3 | Value of work in this certificate | 115,500,000 |
| 4 | Less: retention (10%) | (11,550,000) |
| 5 | Less: advance payment recovery (10%) | (11,550,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (23,100,000) |
| 8 | Net amount payable to the contractor | SYP92,400,000 |
Amount in words: Ninety-two million four hundred thousand Syrian pounds only
Retention held up to this certificate: SYP 76.9M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 107,625,000 | 94,425,000 | 13,200,000 | 107,625,000 | 100% |
| Earthworks & foundations | 276,750,000 | 183,125,000 | 27,325,000 | 210,450,000 | 76% |
| Concrete & structural works | 476,625,000 | 222,600,000 | 39,725,000 | 262,325,000 | 55% |
| Mechanical, electrical & plumbing | 369,000,000 | 105,925,000 | 23,300,000 | 129,225,000 | 35% |
| Finishes & external works | 230,625,000 | 41,625,000 | 10,300,000 | 51,925,000 | 23% |
| Testing & commissioning | 76,875,000 | 6,050,000 | 1,650,000 | 7,700,000 | 10% |
| Total | 1,537,500,000 | 653,750,000 | 115,500,000 | 769,250,000 | 50% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Ammar Al-Ahmad
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. Maher Al-Hamawi
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar