PRJ-2026-021On track3PlanningConstructionNot startedDelivered by:Ministry of Transport

Deir ez-Zor Suspension Bridge Reconstruction

Add to watchlist

Rebuilding the suspension bridge over the Euphrates in Deir ez-Zor for pedestrians and cyclists, keeping its architecture, financed by the Syrian Development Fund — in planning and tendering.

Budget (BAC)

SYP 13B

Actual cost

SYP 260M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 13B

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution12 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 April 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

+6

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦2% done against 2% planned⁩.

⁦SPI 1⁩.⁦00⁩, ⁦CPI 1⁩.⁦00⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Reconstruction & InfrastructureSO-2.2Rebuild damaged areas and provide replacement housing

Main initiative

SI-2.2.1Replacement housing & rebuilding damaged areas

Contribution to the initiative⁦25%⁩

The project’s share of the initiative’s project budget (3 projects)

Secondary links

Annual work-plan line
WP-2026-021
Classification
Strategic

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦2%⁩

Awaiting acceptance ⁦0%⁩

Not handed in ⁦98%⁩

1 deliverable accepted

  • Project plan & baseline⁦2%⁩

0 deliverables under inspection or acceptance

    Progress & earned value

    ⁦2⁩ of ⁦5⁩ milestones complete

    Earned-value curve

    Planned, earned and actual to the data date, cumulative, with the forecast cost tail

    • Planned value
    • Earned value
    • Actual cost
    • Estimate at completion
    • Budget at completion

    Budget & commitments

    Commitments are ⁦2%⁩ of budget

    SYP260M/ SYP13B
    Actual spend
    SYP260M
    Committed
    SYP312.5M
    Approved budget
    SYP13B
    Estimate at completion
    SYP13B

    Next milestones

    • 50% of works complete⁦2027-08-29⁩On track
    • Provisional acceptance⁦2028-10-12⁩On track
    • Closure⁦2028-12-31⁩On track

    Waiting on someone

    ⁦0⁩ approvals and ⁦0⁩ open actions on this project

    Approvals & requests

    From «My actions» for this project

    • No approvals pending

    Actions

    ⁦0⁩ open

    • No actions on this project

    Change requests

    Cost and schedule impact

    • No change requests

    Risks & impediments

    1 open risk, exposure SYP 2.3B

    Risk map

    Probability
    5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
    4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
    3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩1Probability: Possible · Impact: SevereHigh · Score ⁦15⁩RSK-0046Bids 18% above the engineering estimate
    2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
    1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
    12345

    Impact

    • Critical0
    • High1
    • Medium0
    • Low0

    Open impediments

    ⁦0⁩ escalated

    • No open impediments

    Deliverables

    ⁦1⁩ of ⁦12⁩ approved

    • Project plan & baseline021-D1 · V1 · CRT-021-01⁦2%⁩Eng. Wael Al-Khawlani2026-08-102026-08-10Approved
    • Monitoring & reporting021-D2 · V0⁦3%⁩Eng. Wassim Al-AzmDue tomorrow2026-10-29Draft
    • Detailed design021-D3 · V0⁦6%⁩Eng. Wassim Al-AzmIn 80 days2027-01-16Draft
    • Permits & approvals021-D4 · V0⁦6%⁩Salma Al-ZaimIn 159 days2027-04-05Draft
    • Site works & excavation021-D5 · V0⁦13%⁩Salma Al-ZaimIn 239 days2027-06-24Draft
    • Structure021-D6 · V0⁦13%⁩Eng. Wael Al-KhawlaniIn 318 days2027-09-11Draft
    • Finishes021-D7 · V0⁦13%⁩Eng. Wassim Al-AzmIn 398 days2027-11-30Draft
    • Supply021-D8 · V0⁦10%⁩Eng. Wael Al-KhawlaniIn 477 days2028-02-17Draft
    • Installation021-D9 · V0⁦10%⁩Eng. Wassim Al-AzmIn 557 days2028-05-07Draft
    • Testing & commissioning021-D10 · V0⁦10%⁩Salma Al-ZaimIn 636 days2028-07-25Draft
    • Provisional acceptance021-D11 · V0⁦7%⁩Eng. Wassim Al-AzmIn 716 days2028-10-13Draft
    • Final acceptance021-D12 · V0⁦7%⁩Salma Al-ZaimIn 795 days2028-12-31Draft

    Team, contracts & documents

    Team

    3 members

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction ProjectsDr. Firas Al-Obaid · Deputy President, StatisticsAbdullah Al-Ujaili · Contracts & Tendering Specialist
    • Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsProject manager (tender stage)P-036wael.alkhawlani@psa.gov.sy⁦30%⁩
    • Dr. Firas Al-ObaidDr. Firas Al-ObaidDeputy President, StatisticsStatistics lead — crossing-traffic survey before and after the bridgeP-016firas.alobaid@psa.gov.sy⁦25%⁩
    • Abdullah Al-UjailiAbdullah Al-UjailiContracts & Tendering SpecialistSuspension bridge reconstruction tenderP-038abdullah.alujaili@psa.gov.sy⁦30%⁩

    Contracts

    0 contracts

    • No external contracts — delivered in-house