PRJ-2026-021On track3PlanningConstructionNot startedDelivered by:Ministry of Transport

Deir ez-Zor Suspension Bridge Reconstruction

Add to watchlist

Rebuilding the suspension bridge over the Euphrates in Deir ez-Zor for pedestrians and cyclists, keeping its architecture, financed by the Syrian Development Fund — in planning and tendering.

Budget (BAC)

SYP 13B

Actual cost

SYP 260M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 13B

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution12 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 April 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SYP 13B split into spent, committed and left, with the estimate at completion

EAC SYP 13B
Revised request SYP 13B
  • Actual spendSYP 260M
  • Committed, not spentSYP 52.5M
  • Allotted, uncommittedSYP 12.3B
  • Contingency availableSYP 390M

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SYP 12.7B
Original budgetwhen the first baseline was approved
SYP 13B
Approved budgetafter approved change requests
SYP 13B
Current budgetavailable to spend now
SYP 13B
Revised budgetif the pending changes are approved
SYP 13B

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SYP 312.5M
Contracts0 active contracts
SYP 0
Purchase orders⁦3⁩ orders
SYP 312.5M
Remaining budgetapproved less actual
SYP 12.7B

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SYP 260M
Accrualswork done, not yet invoiced
SYP 10.4M
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SYP 13B
ContingencySYP 260M drawn of SYP 650M
SYP 390M

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSYP 12.7B
ApprovedSYP 13B
Estimate at completionSYP 13B
Approved is SYP 260M (⁦2.0%⁩) above the estimate
The estimate at completion is SYP 260M (⁦2.0%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2026-01-20⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-51021
  • WBS elements⁦5⁩ elements · P-2026-021.01 …
  • Purchase orders⁦2⁩ synced · ⁦1⁩ manual
  • Invoices & certificatesNo certificates
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SYP 260M drawn of SYP 650M

  • Covering realised delivery risks⁦2026-08-29⁩SYP 260M

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSYP MCommittedSYP MActualSYP MEACSYP MVarianceSYP MConsumption
1Management & governance756.60262.11260.00764.44⁦−7.84⁩
2Design & permits1,513.206.430.001,537.09⁦−23.89⁩
3Civil works4,791.8020.370.004,867.46⁦−75.66⁩
4MEP works3,783.0016.080.003,842.73⁦−59.73⁩
5Handover1,765.407.510.001,793.28⁦−27.88⁩
Unallocated contingency390.000.000.00195.00⁦+195.00⁩
Total13,000.00312.50260.0013,000.00⁦+0.00⁩

Budget split

WBS

SYP 13B

Budget

  • Management & governanceSYP 756.6M⁦6%⁩
  • Design & permitsSYP 1.5B⁦12%⁩
  • Civil worksSYP 4.8B⁦37%⁩
  • MEP worksSYP 3.8B⁦29%⁩
  • HandoverSYP 1.8B⁦14%⁩
  • Unallocated contingencySYP 390M⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SYP millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2033-04-04⁩+1,555

SPI(t) ⁦0.39⁩ against the approved finish ⁦2028-12-31⁩

Planned valuePV
SYP 1.5B
The value of the work that should be done by today.
PV
Earned valueEV
SYP 260M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SYP 260M
What has actually been spent on the work done.
AC
Budget at completionBAC
SYP 13B
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.00⁩ SYP M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−1,246.66⁩ SYP M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.00
Value produced per pound spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.17
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SYP 13B
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SYP 12.7B
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.00⁩ SYP M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.00
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSYP 13B
  • If the rest goes to planSYP 13B
  • At cost and schedule performanceSYP 74.1B
  • The PM’s bottom-up estimateSYP 13B
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SYP 13B

Variance at completion: ⁦+0.00⁩ SYP M