PRJ-2026-021On track3PlanningConstructionNot startedDelivered by:Ministry of Transport

Deir ez-Zor Suspension Bridge Reconstruction

Add to watchlist

Rebuilding the suspension bridge over the Euphrates in Deir ez-Zor for pedestrians and cyclists, keeping its architecture, financed by the Syrian Development Fund — in planning and tendering.

Budget (BAC)

SYP 13B

Actual cost

SYP 260M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 13B

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution12 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 April 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to workSYP12.6B⁦17⁩ elements
Unallocated contingencySYP390MSYP 650M
Budget at completionSYP13BPRJ-2026-021
Weighted progress⁦2%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSYP MActualSYP MLinksDeliverables
Project1,007⁦2026-04-05⁩⁦2029-01-06⁩⁦2%⁩12,610.00260.00—
1
Phase317⁦2026-04-05⁩⁦2027-02-16⁩⁦34%⁩756.60260.00—
1.1
WBS element248⁦2026-04-05⁩⁦2026-12-09⁩⁦67%⁩378.30260.000 / 1
1.2
WBS element110⁦2026-10-29⁩⁦2027-02-16⁩⁦0%⁩378.30—1 / 2
2
Phase179⁦2027-01-06⁩⁦2027-07-04⁩⁦0%⁩1,513.20——
2.1
WBS element110⁦2027-01-06⁩⁦2027-04-26⁩⁦0%⁩756.60—1 / 1
2.2
WBS element110⁦2027-03-16⁩⁦2027-07-04⁩⁦0%⁩756.60—1 / 2
3
Phase248⁦2027-05-24⁩⁦2028-01-27⁩⁦0%⁩4,791.80——
3.1
WBS element110⁦2027-05-24⁩⁦2027-09-11⁩⁦0%⁩1,597.27—1 / 1
3.2
WBS element110⁦2027-08-01⁩⁦2027-11-19⁩⁦0%⁩1,597.27—1 / 1
3.3
WBS element110⁦2027-10-09⁩⁦2028-01-27⁩⁦0%⁩1,597.27—1 / 2
4
Phase248⁦2027-12-17⁩⁦2028-08-21⁩⁦0%⁩3,783.00——
4.1
WBS element110⁦2027-12-17⁩⁦2028-04-05⁩⁦0%⁩1,261.00—1 / 1
4.2
WBS element110⁦2028-02-24⁩⁦2028-06-13⁩⁦0%⁩1,261.00—1 / 1
4.3
WBS element110⁦2028-05-03⁩⁦2028-08-21⁩⁦0%⁩1,261.00—1 / 2
5
Phase179⁦2028-07-11⁩⁦2029-01-06⁩⁦0%⁩1,765.40——
5.1
WBS element110⁦2028-07-11⁩⁦2028-10-29⁩⁦0%⁩882.70—1 / 1
5.2
WBS element110⁦2028-09-18⁩⁦2029-01-06⁩⁦0%⁩882.70—1 / 1
Total⁦2%⁩12,610.00260.00