PRJ-2026-021On track3PlanningConstructionNot startedDelivered by:Ministry of Transport

Deir ez-Zor Suspension Bridge Reconstruction

Add to watchlist

Rebuilding the suspension bridge over the Euphrates in Deir ez-Zor for pedestrians and cyclists, keeping its architecture, financed by the Syrian Development Fund — in planning and tendering.

Budget (BAC)

SYP 13B

Actual cost

SYP 260M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 13B

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution12 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 April 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Fields required by the project’s stage (Planning): 15 fields required now.Field settings

Planning and Statistics Authority

Project charter

Deir ez-Zor Suspension Bridge Reconstruction

APPROVEDV2Approved ⁦2026-04-03⁩

1Project identity

Required at this stage
Project name
Deir ez-Zor Suspension Bridge Reconstruction
Project code
PRJ-2026-021
Project sponsor
Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy
Project manager
Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy
Project owner
Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy
Portfolio & programme
Reconstruction & Infrastructure PortfolioDamaged Areas Reconstruction Programme
Type & methodology
Infrastructure · Construction
Current phase
3Planning

2Background & rationale

Required at this stage

Rebuilding the suspension bridge over the Euphrates in Deir ez-Zor for pedestrians and cyclists, keeping its architecture, financed by the Syrian Development Fund — in planning and tendering.

3Objectives

Required at this stage
  1. 1Rebuild damaged areas and provide replacement housing
  2. 2Rehabilitate core energy, water and transport infrastructure

4Scope

Required at this stage

In scope

  • Rebuilding the suspension bridge over the Euphrates in Deir ez-Zor for pedestrians and cyclists, keeping its architecture, financed by the Syrian Development Fund — in planning and tendering.
  • Syrian Arab Building Code compliance
  • An approved plan to keep services running for residents during the works

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Syrian Arab Building Code compliance
  2. 2An approved plan to keep services running for residents during the works
  3. 3Civil-defence requirements

6Deliverables

Required at this stage
1Project management plan⁦2026-05-15⁩
2Main deliverable — stage 1⁦2027-08-29⁩
3Main deliverable — final stage⁦2028-08-13⁩
4Final report⁦2028-12-31⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2026-04-03⁩
  2. Contract signed⁦2026-09-12⁩
  3. 50% of works complete⁦2027-08-29⁩
  4. Provisional acceptance⁦2028-10-12⁩
  5. Closure⁦2028-12-31⁩

8Budget

Required at this stage
  • Main contract⁦72.0%⁩SYP9.4B
  • Supervision & consulting⁦14.0%⁩SYP1.8B
  • Internal team⁦9.0%⁩SYP1.2B
  • Contingency reserve (⁦5%⁩)⁦5.0%⁩SYP650M
The delivering body’s investment-plan allocationsTotalSYP13B

9Timeline

Required at this stage
Start
2026-04-055 April 2026
Baseline finish
2028-12-3131 December 2028
Duration
⁦33⁩ months

10Key risks

Required at this stage
  • High⁦Bids 18% above the engineering estimate⁩

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the unified contracts law (⁦Law 51 of 2004⁩)

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • National Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3⁦Target benefits within 12 months⁩

15Governance structure

Required at this stage
  • Change CommitteeApproves scope, cost and schedule changesWeekly
  • Project Approval CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly