Planning
Project management plan
Schedule, deliverables, risks, communications, quality and benefits
- Form no.
- PSA-PMO-F05
- Template edition
- 2.0
- Version
- V1
- Form date
- 2026-04-30
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-021
- Project
- Deir ez-Zor Suspension Bridge Reconstruction
- Portfolio
- Reconstruction & Infrastructure Portfolio
- Sector
- Development Projects Follow-up Sector
- Sponsor
- Salma Al-Zaim
- Project manager
- Eng. Wael Al-Khawlani
1ScheduleAuto-filled
From the project schedule and its approved baseline.
Start
2026-04-05
Baseline finish
2028-12-31
Forecast finish
2028-12-31
SPI
1.00
| Milestone | Planned | Forecast | Slip |
|---|---|---|---|
| Project plan approved | 2026-10-29 | 2027-02-16 | +110 days |
| Designs approved | 2027-04-05 | 2027-07-04 | +90 days |
| Build complete | 2027-11-30 | 2028-01-27 | +58 days |
| Testing & acceptance complete | 2028-07-25 | 2028-08-21 | +27 days |
| Final handover | 2028-12-31 | 2029-01-06 | +6 days |
2DeliverablesAuto-filled
| Deliverable | Weight | Due | Owner |
|---|---|---|---|
| Project plan & baseline | 2% | 2026-08-10 | Eng. Wael Al-Khawlani |
| Monitoring & reporting | 3% | 2026-10-29 | Eng. Wassim Al-Azm |
| Detailed design | 6% | 2027-01-16 | Eng. Wassim Al-Azm |
| Permits & approvals | 6% | 2027-04-05 | Salma Al-Zaim |
| Site works & excavation | 13% | 2027-06-24 | Salma Al-Zaim |
| Structure | 13% | 2027-09-11 | Eng. Wael Al-Khawlani |
| Finishes | 13% | 2027-11-30 | Eng. Wassim Al-Azm |
| Supply | 10% | 2028-02-17 | Eng. Wael Al-Khawlani |
| Installation | 10% | 2028-05-07 | Eng. Wassim Al-Azm |
| Testing & commissioning | 10% | 2028-07-25 | Salma Al-Zaim |
| Provisional acceptance | 7% | 2028-10-13 | Eng. Wassim Al-Azm |
| Final acceptance | 7% | 2028-12-31 | Salma Al-Zaim |
| Accepted with a certificate | 2% | — | — |
3RisksAuto-filled
| Code | Risk | Score | Response | Owner |
|---|---|---|---|---|
| RSK-0046 | Bids 18% above the engineering estimate | 15 | Mitigate | Eng. Wael Al-Khawlani |
4CommunicationsAuto-filled
| Audience | Need | Frequency | Owner |
|---|---|---|---|
| Project sponsor | Status and decisions needed | Monthly | Eng. Wael Al-Khawlani |
| Project owner | Deliverable status and acceptance dates | Fortnightly | Eng. Wael Al-Khawlani |
| PMO | Data and indicator updates | Weekly | Eng. Wael Al-Khawlani |
| Beneficiaries | What changes and when | At each milestone | Eng. Wael Al-Khawlani |
| Team member | Role | Allocation |
|---|---|---|
| Eng. Wael Al-Khawlani | Project manager (tender stage) | 30% |
| Dr. Firas Al-Obaid | Statistics lead — crossing-traffic survey before and after the bridge | 25% |
| Abdullah Al-Ujaili | Suspension bridge reconstruction tender | 30% |
5QualityAuto-filled
- Peer review of every deliverable before acceptance
- Written acceptance criteria for every deliverable
- A PMO audit at every gate
6BenefitsAuto-filled
| Benefit | Baseline | Target | Owner |
|---|---|---|---|
| No benefits recorded | |||
Approval logChain: Project management plan approval · version 1
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction Projects | Submitted | — | 2026-10-23 13:10 |
| 2 | Methodology review — PMO | Methodology review | Mariam Al-ZoubiPMO — analyst | Approved | — | 2026-10-25 09:42 |
| 3 | Technical acceptance — project owner | Technical acceptance | Approval engineProject owner | Pre-breach alert | — | 2026-10-28 08:00 |
Signatures
Methodology review — PMO
Mariam Al-Zoubi
Approved2026-10-25
Technical acceptance — project owner
Eng. Wassim Al-Azm
Awaiting decision
Cash flow & financial commitment
Rasha Al-Mudarres
Later
Sponsor approval
Salma Al-Zaim
Later