PRJ-2026-021On track3PlanningConstructionNot startedDelivered by:Ministry of Transport

Deir ez-Zor Suspension Bridge Reconstruction

Add to watchlist

Rebuilding the suspension bridge over the Euphrates in Deir ez-Zor for pedestrians and cyclists, keeping its architecture, financed by the Syrian Development Fund — in planning and tendering.

Budget (BAC)

SYP 13B

Actual cost

SYP 260M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 13B

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution12 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 April 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
PSA-PMO-F05
Template edition
2.0
Version
V1
Form date
⁦2026-04-30⁩
In approvalPRJ-2026-021Deir ez-Zor Suspension Bridge Reconstruction

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-021
Project
Deir ez-Zor Suspension Bridge Reconstruction
Portfolio
Reconstruction & Infrastructure Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Wael Al-Khawlani

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2026-04-05⁩

Baseline finish

⁦2028-12-31⁩

Forecast finish

⁦2028-12-31⁩

SPI

1.00

MilestonePlannedForecastSlip
Project plan approved⁦2026-10-29⁩⁦2027-02-16⁩+110 days
Designs approved⁦2027-04-05⁩⁦2027-07-04⁩+90 days
Build complete⁦2027-11-30⁩⁦2028-01-27⁩+58 days
Testing & acceptance complete⁦2028-07-25⁩⁦2028-08-21⁩+27 days
Final handover⁦2028-12-31⁩⁦2029-01-06⁩+6 days

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦2%⁩⁦2026-08-10⁩Eng. Wael Al-Khawlani
Monitoring & reporting⁦3%⁩⁦2026-10-29⁩Eng. Wassim Al-Azm
Detailed design⁦6%⁩⁦2027-01-16⁩Eng. Wassim Al-Azm
Permits & approvals⁦6%⁩⁦2027-04-05⁩Salma Al-Zaim
Site works & excavation⁦13%⁩⁦2027-06-24⁩Salma Al-Zaim
Structure⁦13%⁩⁦2027-09-11⁩Eng. Wael Al-Khawlani
Finishes⁦13%⁩⁦2027-11-30⁩Eng. Wassim Al-Azm
Supply⁦10%⁩⁦2028-02-17⁩Eng. Wael Al-Khawlani
Installation⁦10%⁩⁦2028-05-07⁩Eng. Wassim Al-Azm
Testing & commissioning⁦10%⁩⁦2028-07-25⁩Salma Al-Zaim
Provisional acceptance⁦7%⁩⁦2028-10-13⁩Eng. Wassim Al-Azm
Final acceptance⁦7%⁩⁦2028-12-31⁩Salma Al-Zaim
Accepted with a certificate⁦2%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
RSK-0046Bids 18% above the engineering estimate15MitigateEng. Wael Al-Khawlani

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyEng. Wael Al-Khawlani
Project ownerDeliverable status and acceptance datesFortnightlyEng. Wael Al-Khawlani
PMOData and indicator updatesWeeklyEng. Wael Al-Khawlani
BeneficiariesWhat changes and whenAt each milestoneEng. Wael Al-Khawlani
Team memberRoleAllocation
Eng. Wael Al-KhawlaniProject manager (tender stage)⁦30%⁩
Dr. Firas Al-ObaidStatistics lead — crossing-traffic survey before and after the bridge⁦25%⁩
Abdullah Al-UjailiSuspension bridge reconstruction tender⁦30%⁩

5QualityAuto-filled

  • Peer review of every deliverable before acceptance
  • Written acceptance criteria for every deliverable
  • A PMO audit at every gate

6BenefitsAuto-filled

BenefitBaselineTargetOwner
No benefits recorded

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsSubmitted—⁦2026-10-23⁩ 13:10
2Methodology review — PMOMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2026-10-25⁩ 09:42
3Technical acceptance — project ownerTechnical acceptanceApproval engineProject ownerPre-breach alert—⁦2026-10-28⁩ 08:00

Signatures

Methodology review — PMO

Mariam Al-Zoubi

Approved⁦2026-10-25⁩

Technical acceptance — project owner

Eng. Wassim Al-Azm

Awaiting decision

Cash flow & financial commitment

Rasha Al-Mudarres

Later

Sponsor approval

Salma Al-Zaim

Later

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F05 · version V1

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Eng. Wael Al-Khawlani on ⁦2026-10-23⁩

  1. Methodology review

    Methodology review — PMO

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2026-10-25⁩ at ⁦09:42⁩

  2. Technical acceptance

    Technical acceptance — project owner

    Eng. Wassim Al-Azm · Project owner
    Due todayAction time limit about to lapse · Limit 3 working daysLimit 3 working days · Due ⁦2026-10-28⁩

    Pre-breach alert at ⁦70%⁩ — sent ⁦2026-10-28⁩

    Waiting on Eng. Wassim Al-Azm
  3. Financial approval

    Cash flow & financial commitment

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Delegated to Omar Al-Nahhas

    Limit 2 working days · Expected by ⁦2026-11-01⁩

  4. Technical acceptance

    Sponsor approval

    Salma Al-Zaim · Project sponsor

    Limit 3 working days · Expected by ⁦2026-11-04⁩

Steps that do not apply to this record

  • Plan aligned with the contracts — the condition «Contract link?» does not hold

Previous versions

Every version is kept with its status and what changed.

  1. V2In approval⁦2026-04-30⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Eng. Wael Al-Khawlani

  2. V1Returned for editCurrent⁦2026-04-16⁩

    First draft — returned to complete the quality plan

    • Plan from the methodology template

    Eng. Wael Al-Khawlani