Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

RSK-0046Deir ez-Zor Suspension Bridge Reconstruction

Bids 18% above the engineering estimate

15HighOpenMaterial

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Higher construction costs and few bidders for specialist suspension-bridge works

Preventive controls

  • Negotiate with the lowest bidder under the unified contracts law
  • Split the project into two phases

2 / 2

Event

Bids 18% above the engineering estimate

15HighTrigger

Negotiation fails to bring the gap under 10%

Contingency

Re-tender through the General Authority for Supply and Provision with a reduced scope

Impact

A funding gap near SYP 2.34bn, or a re-tender

SYP 2.3B

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
15High

Residual

5
4
3
2
1
1
2
3
4
5
8Medium

Exposure

SYP 2.3B

Residual

⁦47⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 5 days ago

  1. Project manager

    Current level

    Eng. Wael Al-Khawlani

    Currently followed up here
  2. 2

    Programme manager

    Eng. Qasem Al-Hariri

    Automatically at 15 days unreviewed · in 10 days
  3. 3

    PMO director

    Dr. Reem Al-Qabbani

    Automatically at 20 days unreviewed · in 15 days
  4. 4

    Executive Council

    Dr. Samer Al-Daqqar

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦0⁩ of ⁦2⁩ done
  • Negotiate with the lowest bidder under the unified contracts law

    Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy
    In progressIn 23 days2026-11-20
  • Split the project into two phases

    Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy
    Not startedIn 33 days2026-11-30

Trigger

Negotiation fails to bring the gap under 10%

Contingency

Re-tender through the General Authority for Supply and Provision with a reduced scope

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close